1 / 7

Tracker TriP-t Test Stand

Tracker TriP-t Test Stand. Quick Overview Latest Progress Plans/Questions/Options. Terry Hart, MICE Tracker Phone Meeting, March 7, 2007. Hardware Tests of Increasing Fraction of Recorded Muons. Completed TriP-t test stand 2 DG2020 Signal Generators 2 Tektronix P3420 Variable Level Pods

oihane
Download Presentation

Tracker TriP-t Test Stand

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tracker TriP-t Test Stand • Quick Overview • Latest Progress • Plans/Questions/Options Terry Hart, MICE Tracker Phone Meeting, March 7, 2007

  2. Hardware Tests of Increasing Fraction of Recorded Muons • Completed TriP-t test stand • 2 DG2020 Signal Generators • 2 Tektronix P3420 Variable Level Pods • Test board containing TriP-t chip • Fed signals into TriP-t test board. First results: TriP-t seems to function with input zero suppression signal sequence . Next steps: - Check output signal integrity to see if input signals were digitized. - Check if buffering events works.

  3. Data Generator TriP-t Test Board Output Pods

  4. Preamplifier Signals TriP-t Chip Signal Inputs Pipeline Control Signals Program Interface Signals

  5. Test Procedure • Inject charge on input channels every 324 ns. • 4 channels in gate #1 (1,15,16,31) • 3 channels in gate #2 (1,15,31) • 3 channels in gate #3 (15,16,31) • 3 channels in gate #4 (1,16,31) • Check signal outputs on oscilloscope. Pipeline and 4-level analog buffer running during digitization and need to work for a successful test. Terry Hart, MICE Tracker Phone Meeting, March 7, 2007

  6. Tek00000.wfm is TriP-t output Tek00001.wfm is PR1 (start pipeline readout) Tek00002.wfm is MUXCLK Tek00003.wfm is PR1 associated with MUXCLK Tek00004.wfm is TriP-t output Tek00005.wfm is TriP-t for 4 injections Tek00006.wfm is PR1 for 4 injections • PR1 starts pipeline readout • Analog outputs from pipeline • are correct • Digitization times • - 4 channels => 2268 ns • - 3 channels => 1620 ns • Recall inputs • 4 channels in gate #1 (1,15,16,31) • 3 channels in gate #2 (1,15,31) • 3 channels in gate #3 (15,16,31) • 3 channels in gate #4 (1,16,31)

  7. Conclusions and Plans • Test stand has demonstrated that TriP-t can • Run pipeline during digitization • Store data in 4-level analog pipeline for later readout • Next steps • Try to reduce digitization time by ending readout after last hit channel. • Continue to use test stand to guide firmware development. • Perhaps set up AFE-IIt test stand to test entire board. (Can charge be injected into channels as with the TriP-t test stand?). Terry Hart, MICE Tracker Phone Meeting, March 7, 2007