MICE Collaboration Meeting 16 RAL, Oct 2006 Absorber Focus Coil Module – progress & status By

MICE Collaboration Meeting 16 RAL, Oct 2006 Absorber Focus Coil Module – progress & status By Oxford University & all the collaborators on this module. Status on the AFC module Engineering design Absorber; Windows & window connections; Coil design; Cold mass support system;

oriel
Download Presentation

MICE Collaboration Meeting 16 RAL, Oct 2006 Absorber Focus Coil Module – progress & status By

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE Collaboration Meeting 16 RAL, Oct 2006 Absorber Focus Coil Module – progress & status By Oxford University & all the collaborators on this module

  2. Status on the AFC module • Engineering design • Absorber; • Windows & window connections; • Coil design; • Cold mass support system; • Hydrogen delivery system; • Hydrogen cooling loop; • Helium delivery and cooling system; • Power supply; • H T S leads; • Cold intercepts; • Magnet Vacuum cryostat; • AFC main vessel; • Thermal shields; • Vacuum system; • Control & instrumentation

  3. AFC module Engineering • Responsibility • Absorber; • Windows & window connections; • Coil design; • Cold mass support system; • Hydrogen delivery system; • Hydrogen cooling loop; • Helium delivery and cooling system; • Power supply; • H T S leads; • Cold intercepts; • Magnet Vacuum cryostat; • AFC main vessel; • Thermal shields; • Vacuum system; • Control & instrumentation

  4. AFC module Engineering • Responsibility (outstanding) • Absorber; • Windows & window connections; • Coil design; • Cold mass support system; • Hydrogen delivery system; • Hydrogen cooling loop; • Helium delivery and cooling system; • Power supply; • H T S leads; • Cold intercepts; • Magnet Vacuum cryostat; • AFC main vessel; • Thermal shields; • Vacuum system; • Control & instrumentation

  5. Status on the AFC module • Engineering interface • Absorber; • Windows & window connections; • Hydrogen internal pipework; • Crycoolers • Hydrogen delivery pipework; • Vacuum system; • Docking & Ground fixing; • Helium delivery pipework; • Power supply; • Module connections (Bellows); • Venting system; • Control & Instrumentation Cabling; • Liquid Nitrogen delivery system;

  6. Towards a tender specification • Where are we? • The following is a check list of what we have accomplished to date:- • Safety review of the Hydrogen safety; ✔ • R & D work on the Window fixing – welded or bolted ✔ • Safety review of the hydrogen delivery system ✔ • Selection of Cryocoolers; ✔ • Cryogen condense pot, cold intercept connections etc ✔ • Design & validation of the Coil Former & Cold Mass support ✔ • Internal pipework connection design & arrangement ✔

  7. Mini-Flange Test KF16 1mm dia. Indium S-S Mini-Flange Mini Rotation Flange Aluminum

  8. Towards a tender specification • Where are we? • The following is a check list of what we have accomplished to date:- • Safety review of the Hydrogen safety; ✔ • R & D work on the Window fixing – welded or bolted ✔ • Safety review of the hydrogen delivery system ✔ • Selection of Cryocoolers; ✔ • Cryogen condense pot, cold intercept connections etc ✔ • Design & validation of the Coil Former & Cold Mass support ✔ • Internal pipework connection design & arrangement ✔ • Cryostat sizing and module connections ✔ • Creating a tree structure, defining supply & drawingresponsibility, drawing directory etc ✔ • C & Iand thermal performance testof the Absorber ✔

  9. Drawing & design information on the AFC • The repository for all the AFC drawings is at RAL; • Chris Nelson is the keeper of this information; • Oxford (Stephanie Yang) will ensure that Chris gets the latest version of all the cooling AFC drawings; • However, for read only information on the AFC 3-D model, this could be downloaded from our web pageand Stephanie will demonstrate how easy this could be done.

  10. Towards a tender specification • The following is a check list of actions that have not been accomplished:- • Formal response to the H2 R&D review; • Final design details and specifications on:-HTS Leads; Power supply; vacuum pumping; rail & docking system; N2 & helium supply; quench protection etc; • QA procedure for window measurement; • Burst pressure test (3 to 4 sets) for the current window geometry; • Finalising a bidders list, vendor qualification inspection and a set of well defined Tender specification;

  11. Summary • A fair amount of work still to be done before we are ready for tender; • Our priority is on making sure that the interface parameters are well defined and that the tolerances are achievable; • We are still getting feed back from the Spectrometer solenoid manufacture on how we should improve our tender specifications to avoid expensive changes after contract signing; • The AFC Work Group will be re-activated so that we can received more feed back and suggestions from parties outside RAL and Oxford before we conclude the tender specification;