Information Technology Department Bond Program Implementation Plan January 8, 2013

West Contra Costa Unified School District. Information Technology Department Bond Program Implementation Plan January 8, 2013. Agenda. Project Selection Drivers Fund Allocation and Schedule Determinants Funding Need Schedule Budget for 2013 Project Implementation Schedule.

radley
Download Presentation

Information Technology Department Bond Program Implementation Plan January 8, 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. West Contra Costa Unified School District Information Technology Department Bond Program Implementation Plan January 8, 2013

  2. Agenda • Project Selection Drivers • Fund Allocation and Schedule Determinants • Funding Need Schedule • Budget for 2013 • Project Implementation Schedule

  3. Project Selection Drivers • Compliance • Instructional Technology • Infrastructure

  4. Fund Allocation and Schedule Determinants • Online Assessment compliance by 2014 • Common Core requirements • Curriculum & Technology Integration • Digital Equity

  5. Year Amount ($M) Cumulative ($M) 2013 20 20 2015 8 28 2017 5 33 2019 2 35 Funding Need Schedule

  6. Budget for 2013 * Requires legal vetting

  7. Budget for 2013 (Cont’d)

  8. Project Implementation Schedule

  9. Thank You