LHC-b Outer Tracker Schedule. Jan Spelt. A provisional approach for project completion. Deliverables To see what could be within our capabilities On the basis of what is known at this very moment To be within CERN installation schedules Milestones for Design and Production Readiness Reviews
E N D
LHC-b Outer TrackerSchedule Jan Spelt
A provisional approach for project completion • Deliverables • To see what could be within our capabilities • On the basis of what is known at this very moment • To be within CERN installation schedules • Milestones for Design and Production Readiness Reviews • Milestone for installation start at Cern • Manpower estimates for production and installation LHC-b OTR Schedule/Jan Spelt
LHC-b LHC-b OTR Schedule/Jan Spelt
Bridge frame Ruud Arink Herman BoerRookhuisen LHC-b OTR Schedule/Jan Spelt
Front-end box C-frame & services service boxes LV box Henk Schuilenburg LHC-b OTR Schedule/Jan Spelt
Front End Box mechanics LHC-b OTR Schedule/Jan Spelt
GOL/Aux Board X 1 Front End Box elec. X 2 X 2 TDC boards Tom Sluijk Ad Berkien ASD boards X 4 HV boards X 8 LHC-b OTR Schedule/Jan Spelt
Medium Scale Test (MST) LHC-b OTR Schedule/Jan Spelt
Tom Sluijk Uli Uher LHC-b OTR Schedule/Jan Spelt
Deliverables (bridge, frame and services) LHC-b OTR Schedule/Jan Spelt
Deliverables (modules and front ends) LHC-b OTR Schedule/Jan Spelt
Deliverables (Half and full width Front End Boxes) LHC-b OTR Schedule/Jan Spelt
Quality Assurance • To assure all produced elements meet required specification • The QA system should incorporate: • Stock registration • Traceability of components and materials applied • Storage of Quality Data & Documents • Assembly procedures and registration • Test procedures, data registration & test equipment • Procedures for final approval and rejection • Operator names and remarks • A MS Access Data Base system • Text Oriented Data files with a similar layout. LHC-b OTR Schedule/Jan Spelt
Stock database Assembly manager software Production database FE Box Ass. & QA registration FE Box tables Assembled items to installation Comp. tables Boards Ass. & QA registration Board tables Material in for production Ass. & QA registration Services tables Cabling & Services Manuals & Test equip. Quality Data Base (Comp. Data) Quality Data Base (Test Data) Quality Assurance System (front end items) LHC-b OTR Schedule/Jan Spelt
Overall schedule LHC-b OTR Schedule/Jan Spelt
Bridge LHC-b OTR Schedule/Jan Spelt
Module assembly Now > 40 % ready LHC-b OTR Schedule/Jan Spelt
Production speed LHC-b OTR Schedule/Jan Spelt
Module frames LHC-b OTR Schedule/Jan Spelt
½ Module connection LHC-b OTR Schedule/Jan Spelt
Electronic overall LHC-b OTR Schedule/Jan Spelt
FE items LHC-b OTR Schedule/Jan Spelt
Cern installation LHC-b OTR Schedule/Jan Spelt
Milestones • PRR Electronics April 26th (after MST and beam test evaluation) • Start Bulk Production Electronics May 1 • Design Review & PRR Bridge & frames April 1st • Start Bridge & frame production Mid April • ½ Module connection DR & PRR > April 26th • Start Cern installation November 9th • Installation completion End of March 2006 LHC-b OTR Schedule/Jan Spelt
Issues • The schedule is very tight, there is almost no slack • Fine tuning with Cern schedule in progress • Almost everything will be contracted out (prod. drawings ??, proto types ??) • All components delivered like a box of building blocks • Where to assemble the module frames Nikhef<>Cern • Frame assembly and module installation not together • Module installation not in situ • QA, test and test equipment not all covered LHC-b OTR Schedule/Jan Spelt
Quality Assurance, traceability & stock control • Use of modified module assembly stock registration • Adaptation of the module assembly QA system • Use of modified module assembly data base system • Definition of test equipment and procedures • Definition of Quality Limits LHC-b OTR Schedule/Jan Spelt
Delivery related manpower needs • Module production by Wa and Hd covered • Module production Ni, 6.5 man, till the end of 2005 • El. design and production Ni, 3 man from ET plus 1 technician till the end of 2005. First half of 2006, installation peak, not yet estimated • El test setup not all covered, discussion ET • At least ½ man year software from CT • El. production Hd (GOL, Fiber and Otis) no clear information • Engineering Ni, 3 man until the end 2005 • MT Ni, 3 man for proto and various jobs till the end of 2005 LHC-b OTR Schedule/Jan Spelt
Manpower needs for Cern installation • Possible sequence: • Start frame assembly at Cern in the course of October during ~12 weeks • Start module installation in the course of December during ~12 weeks • 2 to 3 people from October till the end of November 2005 • 5 to 6 people from December till mid February 2005 • 2 to 3 people from mid February till the end of March 2005 LHC-b OTR Schedule/Jan Spelt
Nikhef manpower needs to completion LHC-b OTR Schedule/Jan Spelt
To conclude • This schedule is: • Preliminary • To be agreed by collaborating colleagues • Rather tight, few slack • To be synchronized with Cern group • Quality issues in progress • Completion at April 1st !!!!!! 2006 • It is tough to meet this schedule However:Where there is a will, there is a way LHC-b OTR Schedule/Jan Spelt