300 likes | 308 Views
This report provides an overview of the Country Club Creek Trail project, including its goals, recommended route, evaluation criteria, and next steps. It also includes information on the project team, funding, and construction estimates.
E N D
Country Club Creek TrailPreliminary Engineering ReportPublic Outreach Jessica V. Salinas COA Project Manager December 9, 2014
Country Club Creek Trail Agenda • Introduction of Project Team • Overall Program Goals for Urban Trails • Country Club Creek Trail Summary • Preliminary Engineering Report Overview • Outline of PER • Evaluation Criteria • Recommended Route • Next Steps • Questions jvsalinas
Project Team • City Project Sponsor – Nadia Barrera, PWD • City Project Manager – Jessica Salinas, PWD • Project Consultant & Subconsultants: • Civil Engineering Consultants – Gary Martin & Ken Thomas • CAS Consulting, Inc. – Cost Estimating and Utility Coordination • Harutunian Engineering, Inc. – Lighting Options • Hicks & Company – Environmental Investigation • HVJ – Geotechnical Investigation • Jaster Quintanilla San Antonio, LLP – Preliminary Structural Design • Macias & Associates, L.P. – Surveying and Parcel Information jvsalinas
Program Goals for Urban Trails • Easy access for transportation & recreation users. • Link to bicycle & sidewalk network. • Adequate size to accommodate recreation & transportation uses. • Incorporate amenities & features that transform them into unique greenways that reflect the City around them. • Provide adequate resources to maintain & operate. • Ensure context-sensitivity & environmentally sustainability as well as preservation and improvement upon wildlife habitat. nbarrera
Country Club Creek Trail Project Summary • Project Funded by 2010 Prop 1 & 2012 Prop 12 • Preliminary Engineering Report: April 2014 – February 2015 • Design Phase: Spring 2015 – Spring 2016 • Construction Estimate (w/20% Contingency) - $4,519,892 • Construction – Pending Project Funding • Anticipated start Fall 2016 • Project website: http://www.austintexas.gov/urbantrails jvsalinas
Trail Vicinity Map jvsalinas
Country Club Creek Trail • Approximately 3-mile multi-use path generally running along Country Club Creek connecting Lady Bird Lake to Mabel Davis Park in southeast Austin. • Two segments of the trail that need to be constructed • 0.5 mile trail section - from Ventura Drive to Burleson Road through an existing City of Austin electric easement. • Note: Existing segment along Pleasant Valley from Burleson Road to East Oltorf. • 1 mile section - from East Oltorf to the existing gravel trail just north of Elmont Drive. jvsalinas
Preliminary Engineering Report The Preliminary Engineering Report consists of the following sections: Executive Summary Environmental Issues Introduction Utilities Impact Preliminary Trail Routes Structural Preliminary Design Evaluation Criteria Lighting Options Critical Water Quality Zone Opinion Of Probable Cost Erosion Hazard Zone Route Evaluation Drainage and Floodplain Recommended Option Right-of-Way Summary & Next Steps Trees cec
Evaluation Factors The following factors were used to evaluate the different trail segments: Accessibility Right-of-Way Connectivity Obstructions Critical Water Quality Zone Tree Impacts Erosion Hazard Zone Environmental Floodplain/Drainage Impacts Cost cec
TRAIL ROUTE cec
SEGMENT 1 Austin Energy right-of-way (ROW) from Ventura Drive to Burleson Rd Existing Austin Energy Easement jvsalinas
SEGMENT 1 Austin Energy right-of-way (ROW) from Ventura Drive to Burleson Rd Electric power ROW looking north from Ventura. jvsalinas
Segment 2 – Existing Route along S. Pleasant Valley from Burleson to Oltorf jvsalinas
SEGMENT 3 starting at S. Pleasant Valley Rd & E. Oltorf to Riverside Dr. jvsalinas
SEGMENT 3 starting at S. Pleasant Valley Rd & E. Oltorf to Riverside Dr. Oltorf facing west towards Pleasant Valley Looking south towards Riverside Dr. jvsalinas
SEGMENT 3B Segment near Sheringham Dr jvsalinas
SEGMENT 4 starting at Riverside Dr. to Elmont Dr. Northern Bridge of E. Riverside Dr from Wickersham Lane. Wickersham Dr looking north from E. Riverside Dr. jvsalinas
SEGMENT 4 Riverside Dr. to Elmont Dr. jvsalinas
SEGMENT 4 Riverside Dr. to Elmont Dr. jvsalinas
SEGMENT 4 Wickersham Pavement Markings (West Side) jvsalinas
SEGMENT 4 Wickersham Pavement Markings (West Side) jvsalinas
SEGMENT 4 Wickersham Pavement Markings (East Side) jvsalinas
Construction Estimate Section 1 & 2 Section Base Estimate20% Contingencyw/Lighting 1 $371,575 $445,890 $692,644 2 $35,362 $42,435 $352,345 jvsalinas
Construction Estimate Section 3 & 4 Section Base Estimate20% Contingencyw/Lighting 3B1 $1,166,366 $1,399,640 $1,840,336 3C $1,406,156 $1,687,387 $1,834,286 4B1 $787,116 $944,539 $1,549,733 TOTAL$3,766,575$4,519,891$6,269,344 jvsalinas
Next Steps • Dec 2014: Collect Public Input to PER • Open House • City Website • Jan 2015: Project Team to incorporate Feedback and update PER • Jan 2015: City Stakeholder Final Review of PER • Feb 2015: Follow-up Open House to present Final PER • Spring 2015: Design Phase jvsalinas
QUESTIONS jvsalinas
TRAIL ROUTE cec
BACK-UP jvsalinas
Evaluation Factors (continued) • Accessibility – Primarily deciding how easy it is to comply with ADA requirements in a segment. • Connectivity – The ease of reaching destinations from the proposed trail. • Critical Water Zone (CWQZ) – Indicates whether or not the trail segment is located in this zone. • Erosion Hazard Zone (EHZ) – Indicates whether the trail segment is in the EHZ or not. • Floodplain/Drainage Impacts – Indicates whether or not the trail segment is located in the floodplain and if there are any negative impacts to drainage. • Right-of-Way – Indicates if a new easement is required in a trail segment. • Obstructions – Indicates if there are features that would impact the location of the trail. • Tree Impact – Indicates the impact to trees in a trail segment. • Environmental – Indicates the whether or not environmental permits would be required. • Cost – Indicates the relative cost in relation to the other options. cec