1 / 29

Hall C Users Meeting SHMS Structure Installation A pictorial review

M. Fowler Hall C Users Group, 2014. Hall C Users Meeting SHMS Structure Installation A pictorial review. Mike Fowler Hall C Engineering 21 Feb 2014. M. Fowler Hall C Users Group, 2014. August 2013.

reyna
Download Presentation

Hall C Users Meeting SHMS Structure Installation A pictorial review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. M. Fowler Hall C Users Group, 2014 Hall C Users MeetingSHMS Structure InstallationA pictorial review Mike Fowler Hall C Engineering 21 Feb 2014

  2. M. Fowler Hall C Users Group, 2014 August 2013 Structure assembly well underway

  3. M. Fowler Hall C Users Group, 2014 8 August 2013 Back almost complete

  4. M. Fowler Hall C Users Group, 2014 14 August 2013 Magnet wings go on

  5. M. Fowler Hall C Users Group, 2014 19 August 2013 Beamline wall goes up

  6. M. Fowler Hall C Users Group, 2014 21 August 2013 Structure assembly well underway

  7. M. Fowler Hall C Users Group, 2014 30 August 2013 Platform pads are in

  8. M. Fowler Hall C Users Group, 2014 9 September 2013 Sitting on wheels

  9. M. Fowler Hall C Users Group, 2014 12 September 2013 Structure complete, concrete forming started

  10. M. Fowler Hall C Users Group, 2014 19 September 2013 Forms taking shape

  11. M. Fowler Hall C Users Group, 2014 23 September 2013 Rebar arrives

  12. M. Fowler Hall C Users Group, 2014 27 September 2013 Ready to pour floor

  13. M. Fowler Hall C Users Group, 2014 27 September 2013 New floor

  14. M. Fowler Hall C Users Group, 2014 30 September 2013 Wall forms begin to go up

  15. M. Fowler Hall C Users Group, 2014 15 October 2013 First wall pour

  16. M. Fowler Hall C Users Group, 2014 28 October 2013 Second wall pour

  17. M. Fowler Hall C Users Group, 2014 29 October 2013 Beamline wall form goes up

  18. M. Fowler Hall C Users Group, 2014 1 November 2013 Beamline wall pour

  19. M. Fowler Hall C Users Group, 2014 6 November 2013 Forms begin to come down

  20. M. Fowler Hall C Users Group, 2014 7 November 2013 Pretty new walls

  21. M. Fowler Hall C Users Group, 2014 25 November 2013 Boron concrete pour

  22. M. Fowler Hall C Users Group, 2014 2 January 2014 Boron concrete forms come down, roof started

  23. M. Fowler Hall C Users Group, 2014 21 January 2014 Swing door poured, roof forming progressing

  24. M. Fowler Hall C Users Group, 2014 27 January 2014 Utility platform begins

  25. M. Fowler Hall C Users Group, 2014 6 February 2014 Transfer line goes up

  26. M. Fowler Hall C Users Group, 2014 Today Platform up, roof blocks poured

  27. M. Fowler Hall C Users Group, 2014 Additional reading at: CONCRETEPRODUCTS.COM

  28. M. Fowler Hall C Users Group, 2014 Video By: Walt Akers YouTube http://www.youtube.com/watch?v=w4Q7izUnXU0

  29. M. Fowler Hall C Users Group, 2014 Door hinge Target platform Lead in the hut Computer floor Power supplies Utilities Cryo HVAC Detectors & MAGNETS To Be Done

More Related