1 / 25

Welcome to Pinal County

Welcome to Pinal County. The Three C’s of Hunt Highway. Greg Stanley Pinal County Public Works. AACE Regional Conference Oct 1-3, 2008. Agenda. Background Project Specifics Phase I & DCR - Scope, Project Limits & Schedule The 3 C’s (Phase I) Cooperation (Communication & Coordination)

rhett
Download Presentation

Welcome to Pinal County

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Welcome to Pinal County

  2. The Three C’s of Hunt Highway Greg Stanley Pinal County Public Works AACE Regional Conference Oct 1-3, 2008

  3. Agenda • Background • Project Specifics • Phase I & DCR - Scope, Project Limits & Schedule • The 3 C’s (Phase I) • Cooperation (Communication & Coordination) • Agencies, Development, Utilities & Right-of-way • Complexity • Drainage, Fissures, Traffic • Creative Solutions • Drainage Channels, Fissure Mitigation Measures, Construction Phasing/Traffic Control Plan

  4. Background • Explosive Growth Over Past 5 Years • 5 Major Master planned Communities • Existing 2-lane facility, some areas of new development widened to 5-lanes • 20,000+ on average vehicles per day • With the Ironwood Project now complete, widening Hunt Hwy is Pinal County’s #1 Transportation Priority

  5. Project Specifics - Scope • May ’07 (SOQ process) hired RBF Consulting as Design Engineer • Within 1-year from NTP: • 100% PS&E for Phase I – Empire Blvd to Thompson Rd • DCR for entire 12-Mile corridor from Empire to Town of Florence Limits • Project originally scoped between Empire Blvd and just west of Thompson Rd • Revised Oct ’07 to include full Thompson Rd intersection improvements • Revised April ’08 drainage channel design • Revised July ’08 to include raised median for access control

  6. Phase I - Scope • Phase I – Empire Blvd to Thompson Rd • 5-lane minor arterial section, two through, raised median, 4.5’ paved shoulders • Drainage channel design (Sonoqui Wash) • J-curve commercial property • North side of Hunt Hwy from Valley View Rd to J-curve

  7. Phase I - Scope • Phase I – Empire Blvd to Thompson Rd (cont’d) • 5 major culvert crossings • Empire Blvd (2,400 CFS) • End of J-curve (2,300 CFS) • Valley View Rd (400 CFS) • Thompson Rd (660 CFS) • 1200’ East of Thompson Rd (900 CFS) • Traffic signals • Empire Blvd • Thompson Rd

  8. Phase I - Project Limits

  9. Design Concept Report (DCR) • Empire to Town of Florence Limits (~12 Miles) • Analyzes “future” 7-lane principal arterial section • Right-of-way • Utilities • Relocations • Traffic Engineering • Drainage • Geotechnical • Environmental • Land use

  10. DCR Limits

  11. Phase I - Schedule • Funding Constraints • Initially to be Development funded (Impact Fees) • Slowdown in market • Previous Development Agreements • Currently looking into… • Greater Arizona Development Authority (GADA) funding • Highway Expansion & Extension Loan Program (HELP) funding Pinal County Hunt Hwy Fund

  12. Phase I - Schedule • Schedule • 100% PS&E for Phase I – Sept/Oct ‘08 • Construction • Bid process Nov/Dec ‘08 • GADA/HELP loan secured in Dec ’08 • Start construction Jan ’09 (8-10 Mos)

  13. Cooperation (Communication & Coordination) • Agencies • Empire Blvd/Ellsworth Rd Intersection • Town of Queen Creek • Maricopa County • MCDOT • FCDMC • MCDOT/Queen Creek’s Ellsworth Rd Project – Empire Blvd to Cloud Rd • 7-lane improvement

  14. Cooperation (Communication & Coordination) • Development • Commercial • J-curve Property (San Tan Gateway) • San Tan Commons • Store More Self Storage • H2T2 • San Tan Borgata Commercial • Borgata Professional Development Plaza • Residential • San Tan Shadows • San Tan Heights

  15. Cooperation (Communication & Coordination) • Developers / Engineers / Utilities • On-going coordination meetings • Design • Right-of-way • Construction Scheduling • Who will be there first…

  16. Cooperation (Communication & Coordination) • Property Owners & Right-of-Way • 36 properties • 13AC right-of-way • 8.5AC drainage easements • Meeting w/ each owner individually • Explanation of project, given copies of legal's, copies of plans/reports, etc. • Appraisal completed (outside consultant) • Meeting again w/ owner acquisition agreement drafted

  17. Complexity • Attempting to Provide “Regional” Drainage Solution with 3-mile Widening Project • Regional Drainage Solution has to balance: • Proposed Commercial and Residential Development Individual Drainage Solutions • Existing Drainage Conditions – Roadway Closures During Even Minor Storm Events • Current Pinal County and FCDMC Guidelines • Empire Box Culvert • Prone to heavy sediment deposits • Downstream Sonoqui Wash not well defined – adjacent properties within floodplain

  18. Complexity • Drainage Complexity Overview

  19. Complexity • Fissures within the Project Area

  20. Complexity • Traffic • 20,000 ADT • Equivalent to Broadway Rd, Southern Ave in Phoenix and Orange Grove Rd, Stone Ave in Tucson • Very Limited Alternate Routes • Up to 7’ Vertical Difference During Construction • Due to Culvert Crossings • Construction Phasing • Hunt Hwy/Empire Blvd Intersection • Access Management

  21. Creative Solutions • Drainage Channels • Location/Alignments • Balance of Good Hydraulic Design with R/W and Drainage Easement Impacts

  22. Creative Solutions • Fissure Mitigation • Interceptor Trenches/Fissure Mitigation Trenches

  23. Creative Solutions • Traffic • Temporary Pavement • Create Separation from Work Zone Near Areas of Large Fill Heights • Phasing of Improvements • Hunt Hwy/Empire Blvd Intersection – 3 Phase Construction including Detour Plan

  24. Creative Solutions • Traffic (cont’d) • Access Management & Control

  25. Questions?????

More Related