An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CONVENTIONAL FACILITIESLCLS Office Space Procurement Jess Albino – Associate Project Director for Civil Construction May 14, 2009

  2. Agenda • Status • LCLS Office Space Advance Procurement Plan • Baseline – Renovation of B028 and B751 • Guaranteed Maximum Price Contract

  3. LCLS Office Space Advance Procurement Plan

  4. Baseline Procurement Plan Contract Type: Firm Fixed-price Single Contract to renovate both B028 and B751 HDR is Engineer-of-record; will provide Title III services during construction Construction Management consultant for Title III Commissioning Agent

  5. Office Space Schedule Construction CompleteMarch 26, 2010 A/E Design CompleteJune 1, 2009 Award/NTP ConstructionJuly 29, 2009

  6. Office Space Procurement • Alternative (not in baseline) • Guaranteed Maximum Price Contract • Firm fixed-price • Performance Specifications • Conceptual Design provided • Construction to complete end of April, 2010 • Contract completion 1 Quarter prior to CD-4

  7. Office Space Procurement • Letters of Interest • Provided industry feedback • Provided notice-of-intent to advertise • Provided opportunity to form Teams • Prospective bidders list • Evaluated and categorized based on safety performance and prior experience • Developed further interest in the project • 7 Teams requested and received bid package • 5 proposals received • Evaluation and Selection based on Best Value • Award • Breaking ground first part of August • Occupy new building in April, 2010.

  8. New Building

  9. end of presentation

  10. BACK UP INFORMATION

  11. Experience at LLNL • “$5M buildings” at LLNL • Similarly Spartan office buildings for project teams • Minimum risk to bidders • Price is fixed, bidders propose square footage

  12. Fast-track Building Construction

  13. Fast-track Building Construction

  14. Fast-track Building Construction

  15. Alternate building site (near CEH) Near Experimental Hall Loop Road Potential Building Site Central Laboratory Office Complex

  16. New Building Site Plan

  17. New Building Elevations

  18. New Building

  19. Cost Estimate - Conceptual

  20. Construction Schedule - Conceptual