1 / 6

SIS 2006 Update

SIS 2006 Update. May 24, 2006. Big Picture.  Design Phase Preparatory Projects Phase – April 24 – August 4 Configuration Documentation & Testing Reconfigure K12/HAN/Library, Co-locate w/ Internet provider, local projects Implementation – ?August 5? – ?????

rogan-reid
Download Presentation

SIS 2006 Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SIS 2006 Update May 24, 2006

  2. Big Picture •  Design Phase • Preparatory Projects Phase – April 24 – August 4 • Configuration Documentation & Testing • Reconfigure K12/HAN/Library, Co-locate w/ Internet provider, local projects • Implementation – ?August 5?– ????? • Details to be determined…again

  3. Current Risks/Issues • Grand Forks Fiber • Delays in getting approvals and sign-offs • Assume redundant fiber link will not be available by rollout • Continued delay in DCN turnover • Revising rollout again • Focus on minimizing impact to HE & K12

  4. Good News • Equipment is starting to arrive • Lab is up and configuration & testing has begun

  5. More Information • Next IVN Session = June 28 • www.stagenet.nd.gov/projects/infrastructure/index.html • Biweekly status reports • Conceptual diagrams • Dirk Huggett • dhuggett@nd.gov • 701-223-2248

  6. Questions

More Related