North Mankato Load Serving study

Explore system characteristics, major loads, and preferred plan for the North Mankato Load Serving Study area by Xcel Energy & Great River Energy. Learn about critical contingencies, future 115 kV line additions, and other concerns.

sbecerra
Download Presentation

North Mankato Load Serving study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. North Mankato Load Serving study Xcel Energy Great River Energy

  2. Study Area:

  3. System Characteristics • Major loads include Cities of Lesure and St. Peter • Only two strong sources from Wilmarth. • Long 69 kV lines.

  4. Critical contingencies (2012):

  5. Critical contingencies continued:

  6. Preferred Plan: • Preferred Plan is option 2. • Relatively inexpensive. • Scope for future 115 kV line additions from Helena substation.

  7. Other Concerns: • SPS to trip the Helena – St. Thomas line for the loss of Helena – Wilmarth or Helena – Blue Lake 345 kV lines. • The inservice date for this project depends on the inservice date of Helena 345 kV substation. The project schedules has to be coordinated with the Southwest Minnesota – Twin cities 345 kV line.

  8. Questions?