70 likes | 182 Views
SIS 2006 Update. September 27, 2006. Big Picture. Design Phase Preparatory Projects Phase Implementation – Began migration on Tuesday Overall schedule has not changed. Implementation. Sept 18–Oct 6 – Test & Migrate Bismarck-Fargo ATMs to RPR
E N D
SIS 2006 Update September 27, 2006
Big Picture • Design Phase • Preparatory Projects Phase • Implementation – Began migration on Tuesday • Overall schedule has not changed
Implementation • Sept 18–Oct 6 – Test & Migrate Bismarck-Fargo ATMs to RPR • Sept 25–29 – Burn-in time for RPR, Prep for PSD migration • Sept 30–Oct 6 – Migrate PSD • Oct 7–14 – Migrate I2 and prep for K12 • Oct 16–Nov 3 – Migrate K12 • Oct 23–28 – Migrate K12 Video • Oct 23 – Nov 17 – Prep & Migrate State • Nov 4–Nov 25 – Prep & Migrate HE
Current Risks/Issues • Sprint Collocation – Waiting on rack
Good News • All testing completed • Migration started • Contact our Customer Service Desk at 701-328-4470 if you experience any issues.
More Information • Next IVN Session = October 25 • www.stagenet.nd.gov/projects/infrastructure/index.html • Biweekly status reports • Presentations • Dirk Huggett • dhuggett@nd.gov • 701-223-2248