1 / 16

Marknadsinformation – UMM-rapporten

Marknadsinformation – UMM-rapporten . Status – det fortsatta interna arbetet Elmarknadsrådet 2008-03-04 Jakob Katzman, Svenska Kraftnät Drift. Genomfört. UMM vid mothandel (tidsperiod, volymsintervall, orsak)

sharne
Download Presentation

Marknadsinformation – UMM-rapporten

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Marknadsinformation – UMM-rapporten Status – det fortsatta interna arbetet Elmarknadsrådet 2008-03-04 Jakob Katzman, Svenska Kraftnät Drift

  2. Genomfört • UMM vid mothandel (tidsperiod, volymsintervall, orsak) • UMM med avtalad effektreserv för mothandel, körning av nätskäl (ändrad beredskapstid, start, stopp, tripp) • Beslutade investeringsprojekt som påverkar handelskap. informeras på lämpligt sätt (UMM, Exchange Info etc.)

  3. På gång • Internt dokument • Handledning (dokumentera det gjorda, olika fall, vem initierar, göra/uppdatera färdiga textförslag, … )Sammanställa/uppdatera befintliga dokument. • Utbildningsförslag (internt (handledning+regelverk), externt (NPS om marknaden, insider mm), belysa för HELA organisationen) • Uppdaterad UMM-applikation (NPS) • Transparens inom Nordel

  4. Intern handledning • Sammanfattning av NPS:s User manual, TSO guidelines och Data Publication Agreement • Definierade huvudkategorier för UMM inkl. malltexter och interna rutiner: • Nätskäl • Nätskäl mha effektreserv • Balansskäl vinter/övrig tid

  5. Nätskäl • Snittproblem etc. (mothandel) • Störning (mothandel, ”failure”, instängd produktion mm.) • Planerade avbrott • Underhåll (kap. på utlandsförb., instängd produktion mm.)Interna rutiner uppdateras • Investeringsprojekt (UMM samt ev. Exchange Info motsv.). Interna rutiner definieras. Dessutom kommer beslutade nordiska projekt att listas i ett TSO-dokument på NPS.

  6. UMM vid mothandel (”Countertrade”)Varför? • Vid mothandel, t.ex. över Konti-Skan, Baltic Cable, SwePol Link och/eller reglering av kärnkraft och värmekraft för att t.ex. innehålla gällande snittgränser mm., kommer elen ibland att flyta ”i fel riktning” marknadsmässigt, dvs från ett högpris- till ett lågprisområde.

  7. När skicka? • Mothandel >100 MW • Då mothandelsbehovet är känt eller föreligger (vid oplanerad händelse) i driftskedet • Inte planera handelskapaciteten med mothandel

  8. Innehållet i UMM • Att det avser mothandel • Orsak • Tidsperiod • Volymsintervall

  9. Exempel Special information - Details given in remarks below Message Time: 16.12.07 hour 19:35 Decission Time: 16.12.07 hour 19:30 Approved: 16.12.07 hour 19:35 Company: Svenska Kraftnät Affected areas: SE Line: Counter Trade SE SE to to SE SE Installed outgoing capacity (MW): 0 0 Outgoing capacity before event (MW): 0 0 Outgoing capacity during event (MW): 0 0 Outgoing capacity after event (MW): 0 0 Event start: 17.12.07 hour 06:00 Event stop: 17.12.07 hour 21:00 Event status: Open Remarks/Additional information: ------------------------------- Counter trade may be applied due to cut 2 during 06-21 to an amount of 100-400 MW

  10. Intern handledning • Sammanfattning av NPS:s User manual, TSO guidelines och Data Publication Agreement • Definierade huvudkategorier för UMM inkl. malltexter och interna rutiner: • Nätskäl • Nätskäl mha effektreserv • Balansskäl vinter/övrig tid

  11. UMM för mothandel med avtalad effektreserv • Aggregat • Ändrad beredskapstid • Start • Stopp • Tripp • Volym • Orsak (körning av nätskäl pga. …)

  12. Intern handledning • Sammanfattning av NPS:s User manual, TSO guidelines och Data Publication Agreement • Definierade huvudkategorier för UMM inkl. malltexter och interna rutiner: • Nätskäl • Nätskäl mha effektreserv • Balansskäl vinter/övrig tid

  13. Balansskäl Nivåer av effektbrist definieras (grön, gul, röd). Vinter (effektreserven) • Grön (UMM med speciell marknadsinfo och info om effektreserven) • Effektreserv planeras att aktiveras • Effektreserv aktiveras (start, stopp, aggregat, volym, ev. tripp) • Gul (UMM med marknadsinfo) • Ansträngd situation • Röd (UMM med marknadsinfo) • Fara för effektbrist • Effektbrist • Kritisk effektbrist Körning av icke effektreservsaggregat av balansskäl hanteras som ”vanlig” reglering (avrop), dvs. inga SvK-UMM skickas.

  14. Balansskäl Övrig tid på året • Gul (UMM med marknadsinfo) • Ansträngd situation • Röd (UMM med marknadsinfo) • Fara för effektbrist • Effektbrist • Kritisk effektbrist Körning av icke effektreserv av balansskäl hanteras som ”vanlig” reglering (avrop), dvs. inga SvK-UMM skickas med info om aktivering av störnings-reserver.

  15. Transparens inom Nordel • Lista på NPS med beslutade projekt som påverkar förbindelserna • Ny applikation mm. (NPS i samråd med användare), ”morgondagens” marknadsinformation… (UMM, prognoser mm. i framtiden?). Pres+filter. NPS tar strategiska beslut… • Uppdatera Data Publ. Agreement (5-p. avt), mothandel inom Nordel mm. (Nordel OPG och NPS) • Nordel´s ad-hoc Transparency Working Group

  16. Vad händer • SvK dokument färdigställs (handledning och utbildningsförslag mm.) • Intern genomgång/utbildning för berörda nivåer och användare • Arbete Nordel och NPS för transparens (5-partsavtal mm.) • TWG (TSO-NPS)

More Related