Preparation Forum for WebSAMS Implementation. 蓄勢待發 , 迎 WebSAMS. Presented by. Raymond Li Technical Services Manager NCS. Agenda. Overview of Rollout Process Stage 1 – Readiness Check Stage 2 – School Preparation Major Documents Stage 3 – Schedule Planning
E N D
Document 12 Preparation Forum for WebSAMS Implementation 蓄勢待發, 迎WebSAMS Presented by Raymond LiTechnical Services Manager NCS
Document 12 Agenda • Overview of Rollout Process Stage 1 – Readiness Check Stage 2 – School Preparation • Major Documents Stage 3 – Schedule Planning Stage 4 – WebSAMS Installation Stage 5 – Post-installation • The Support Services
Stage 1 Stage 2 Stage 3 Stage 5 Readiness Check School Preparation Schedule Planning Post-installation Complete Outstanding Tasks Collect & Prepare Related Information • Readiness Assessment .HW & SW • Network • SAMS Stage 4 Ready to use !! Installation Data Conversion SAMS Training Document 12 Roll-out Process Overview - 5 Stages
Document 12 Roll-out Process Overview Stage 1 Readiness Check
HW & SW • Network • SAMS Document 12 Roll-out Process Overview - Stage 1 Readiness Check
Document 12 Roll-out Process Overview - Stage 1 Readiness Check – HW & SW 2 Dedicated Servers - WebSAMS & HTTP Server WebSAMS Server • Mini HW Configure : P III 600 Mhz, 1GB RAM, 3 x 9 GB HD. • Windows 2000, Backup, Anti-Virus Software • Existing SAMS Server
Document 12 Roll-out Process Overview - Stage 1 Readiness Check – HW & SW HTTP Server • PC class • P II 400 Mhz • 128 MB RAM • 4GB HD
Document 12 Roll-out Process Overview - Stage 1 Readiness Check - Network Network Infrastructure Requirement for WebSAMS Rollout 1. The WebSAMS segment and the ITEd segment are separated by a router.
Document 12 Roll-out Process Overview - Stage 1 Readiness Check - Network Network Infrastructure Requirement for WebSAMS Rollout 2. The Internet is separated from the school network by an Internet Gateway (IG).
Document 12 Roll-out Process Overview - Stage 1 3. The IG should be configured to provide the following services: • IP packet filtering; and • Network Address Translation (NAT).
Document 12 Roll-out Process Overview - Stage 1 4. The IG can be a: • Firewall with or without DMZ; • Proxy server; or • Router.
Document 12 Roll-out Process Overview - Stage 1 5. The IG may be implemented by: • ISP; or • School
?? Document 12 Roll-out Process Overview - Stage 1 A Common Fault No IG !! Mix of Internet & Intranet => Security Exposure
Document 12 Roll-out Process Overview - Stage 1 SAMS Readiness • SAMS version 4.4 & CDS 4.1 • Restore archive data from tapes • Update Chinese fonts with HKSCS Big5 codes
Document 12 Roll-out Process Overview Stage 2 School Preparation
Complete Outstanding Tasks • Collect and Prepare the Required Information • Data Conversion SAMS • Training Document 12 Roll-out Process Overview - Stage 2 School Preparation
Document 12 Roll-out Process Overview - Stage 2 Complete Outstanding Tasks • HW & SW • Network • SAMS
Document 12 Roll-out Process Overview - Stage 2 Network Preparation • NAT port mapping for Internet Gateway • ONE-TO-ONE mapping of TCP port 80, 443, and 7010 (for training system). Public (Internet) IP address for WebSAMS's Linux HTTP server & Private (Internal) IP address for WebSAMS's Linux HTTP server For examples 202.82.18.180 TCP 80 -> 10.64.128.25 TCP 80 202.82.18.180 TCP 443 -> 10.64.128.25 TCP 443 202.82.18.180 TCP 7010 -> 10.64.128.25 TCP 7010 • WebSAMS server (e.g. 10.64.143.150) can access to Internet directly WITHOUT using a proxy server The validity will be confirmed by EMB’s contractor before rollout
Document 12 Roll-out Process Overview - Stage 2 Network Preparation Get ready the WebSAMS URL (Convention: websams.schoolabc.edu.hk) • Request ISP to include the DNS entry of WebSMS URL for Internet access • For EMB to generate the digital certificate which is necessary for CDS
Document 12 Roll-out Process Overview - Stage 2 Collect & Prepare Related Information • to be facilitated by Forms collection • WebSAMS Installation Readiness Checklist (Form 2) – to be ready 1 week after the Preparation Forum • Information Required Before WebSAMS Installation (Form 1) • Action List for WebSAMS Implementation (Doc 2e)
Form 1 Form 2 NAT Mapping WebSAMS URL Perform Data Conversion Document 12 Roll-out Process Overview - Stage 2 All in All Immediate information to kick start the rollout preparation • Basic school contact information (e-mail, mobile), through Form 1 & 2 • Confirm the tentative rollout date – for prioritization purpose. EMB’s contractor will follow up. • Network diagram (Form 2) • NAT mapping, ASAP by school • WebSAMS URL application (Form 2) – ASAP by school • Perform data conversion – with the DCV kit can proceed right away.
SAMS Document 12 Roll-out Process Overview - Stage 2 Data Conversion • Data Conversion Kit
Document 12 Roll-out Process Overview - Stage 2 Training • 5 full days comprehensive training
Document 12 Roll-out Process Overview Stage 3 Schedule Planning
Document 12 Roll-out Process Overview - Stage 3 Schedule Planning • Fix the rollout date with EMB’s contractor • Take into consideration of Data Conversion (at least 1 wk before rollout date) • Practice before data conversion Planning Timing
DCV Trial Run Freeze point System checkup Pre- validation Data Conversion Post- validation Pre- validation Data Conversion Post- validation System Checkup Iterative Iterative 2 days System Roll Out Estimate 7 days Document 12 Roll-out Process Overview - Stage 3 Dependencies of Rollout date planning
Document 12 Roll-out Process Overview Stage 4 WebSAMS Installation
Document 12 Roll-out Process Overview - Stage 4 WebSAMS Installation • EMB’s contractor - WebSAMS installation • Installation of WebSAMS server • Installation of HTTP server • Network configuration • Upload converted SAMS data • Handover documentation, software license, account & password • Schools • Immediate – Conduct installation test cases • W/i 3 mandays – Sign-off data conversion acceptance • W/i 3 mandays - Sign-off installation acceptance • After 1 month – Sign-off reliability test
Document 12 Roll-out Process Overview Stage 5 Post-installation
Document 12 Roll-out Process Overview - Stage 5 Post-installation • Send the WebSAMS version number via CDS message to EMB • Change WebSAMS account passwords • Assign WebSAMS initial access right • Modify PC configuration • Routine Security Check • Routine System Backup
Document 12 Support Services Hotline Services from EMB’s contractor • Tel : 3125-8510 • E-mail : websams_support@hk.ncs-i.com • Fax : 3125-8999 EMB Contact – websams_rollout@emb.gov.hk Service Hours - Mon-Fri : 8:30 am - 5:30 pm ; Sat : 8:30 am - 12:00 noon Scope of Services • Pre-installation support • School Preparation • Data Conversion • Administration (e.g. Schedule installation appointment) • Post-installation support • Installation • Technical