PROGRAM EVALUATION REVIEW TECHNIQUE (PERT). Ismu Kusumanto Jurusan Teknik Elektro UIN Sultan Syarif Kasim Riau. FORMULASI. te : weighted average activity time a : optimistic activity time b : pessimistic activity time m : most likely activity time. FORMULASI.
E N D
PROGRAM EVALUATION REVIEW TECHNIQUE(PERT) Ismu Kusumanto Jurusan Teknik Elektro UIN Sultan Syarif Kasim Riau
FORMULASI te : weighted average activity time a : optimistic activity time b : pessimistic activity time m : most likely activity time
FORMULASI TE : critical path duration Ts : scheduled project duration Z : probability
EXAMPLE Berapa probabilitas proyek selesai dalam 67 hari ?
ANSWER 43 3 D 30 B 59 64 A 13 16 F 1 2 5 6 30 5 E C 56 20 6 4 TE = 64
ANSWER • Probabilitas proyek selesai dalam 67 hari adalah : P = 0.69 P = 69 %
LATIHAN Berapa probabilitas proyek selesai dalam 55 hari ?