1 / 10

PERT Program Evaluation and Review Technique

PERT Program Evaluation and Review Technique. Tong Wang 511 D ERB. PERT Example. Consider a small project that involves the following activities. PERT Example (cont’d). (a) Determine the expected value and the variance of the completion time for each activity.

osman
Download Presentation

PERT Program Evaluation and Review Technique

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PERTProgram Evaluation and Review Technique Tong Wang 511DERB

  2. PERT Example Consider a small project that involves the following activities.

  3. PERT Example (cont’d) • (a) Determine the expected value and the variance of the completion time for each activity. • (b) Use the expected times from (a) to find the critical path. • (c) Assuming that the normal distribution applies, determine the probability that the critical path will take between 18 and 26 days to complete. • (d) How much time must be allowed to achieve a 90% probability of timely completion? • (e)By using modified probability of completion method, what is the probability that all paths will take before 18 weeks?

  4. Exercise Solution (a) END E 14.5 A6 D4 C 14 START B7

  5. Exercise Solution (cont’d) (b) By using the expected time (mean) of each activity, we find that the critical path is A-C-D. Remark: For this simple project, we can find the longest path (A-C-D)has the largest expected time, which is the critical path. The mean critical path duration is μ= 6 + 14 + 4 = 24. The variance of the critical path duration is the sum of the variances along the path:   σ2cp = (4+256+4) / 36 = 264/36 so that the standard deviation is readily computed as σcp= 2.708.

  6. Exercise Solution (cont’d) (c)The interval probability may be computed as the difference between two cumulative probabilities as follows:  P(18 ≤ t  ≤  26) = P(t  ≤  26) - P(t  ≤  18). Two separate z computations are required. First at 26 we have  z26= (26-24) / 2.708=0.739 Then by looking up the normal table with z26=0.739, we have one result that P(t ≤ 26) = 0.770

  7. Exercise Solution (cont’d) Secondly, at 18 we have z18= (18-24) / 2.708= -2.216 and P(t  ≤  18) = 0.013 Combining these two results yields the desired probability as  P(18  ≤  t  ≤  26) = 0.770 - 0.013= 0.757.

  8. Exercise Solution (cont’d) (d) For 90% probability, we must pick a z value corresponding to 90% of the area under the normal curve, 50% left of mean and 40% right of mean, so z = 1.282. Then solving for t we have  t = 24 +1.282*2.708 = 27.47 days.

  9. Exercise Solution (cont’d) (e)There are three paths in total. They are A-C-D, A-E, and B-D. • The probabilities for the three paths to be completed 18 weeks are given below. • P(X1≤ 18) = P( z ≤ (18-24) / 2.708) = 0.013 • P(X2≤ 18) = P( z ≤ (18-20.5) / 2.192) = 0.127 • P(X3≤ 18) = P( z ≤ (18-11) / 2.356) = 0.999 • Then the probability of completing all the paths in 18 weeks is • P(X ≤18) = P(X1≤ 18) P(X2≤ 18) P(X3≤ 18) = 0.0016.

  10. Questions?

More Related