An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2014 Construction Plans Jon Chiglo, PE Project Director

  2. Tentative 2014 Construction Timeline

  3. Access to businesses and residences • Local access will remain during business hours and at all times to residences. • Business signage • Detour signage • Temporary gravel roads

  4. 2014 Minn. Approach Work Contracted Maximum Impacts • North Frontage Road—50 calendar days • Osgood Avenue—40 calendar days • Greeley Street—40 calendar days • Oakgreen Avenue—25 calendar days • South Frontage Road—70 calendar days

  5. Highway 36 • Single-lane in each direction – Open AT ALL TIMES • Work: Resurface road • Westbound: Spring to mid-summer 2014(red) • Eastbound: Mid-summer to fall 2014(green)

  6. South Frontage Road – East of Osgood • Closed to through traffic • Local access to businesses and residences • Work: Resurface road, replace public utilities • Spring to mid-summer 2014 (red)

  7. Hwy 95 / Lookout Trail / Sunnyside • Hwy 95 • Single-lane in each direction • Work: Construct 4-lane road • Spring to mid-summer 2014 (red) • Lookout Trail • Work: Reconstruct access to Hwy 95 • to right in/out intersection • Spring to mid-summer 2014 • Sunnyside Marina • Work: Reconstruct driveway • Spring to mid-summer 2014

  8. North Frontage Road • North Frontage Road – Northwestern to Greeley • Possible detours to access North Frontage Road. • Work: Resurface road, add turn lane, add curb & gutter • Spring to mid-summer 2014(red)

  9. North Frontage Road • North Frontage Road – Greeley to Osgood • Possible detours to access North Frontage Road, either from Greeley St. or Osgood Ave. • Permanent closure of right in/out connection to Hwy 36 • Work: Resurface road, add turn lane, add curb & gutter • Spring to mid-summer 2014(red)

  10. Greeley St./Oakgreen Ave. Intersection • North/south traffic closed for 2 periods of 6 calendar days each • Oakgreen—Closed between S. Frontage Road and 58th St./Oak Park Blvd. for 25 days. Local residential access only. (green) • Work: Build new frontage road system further away from Hwy 36; shift intersection to the east; install three traffic signal systems; add double left turn lanes

  11. Osgood Ave. Intersection • North/south traffic closed for 2 periods of 6 calendar days each • Work: Add double left turn lanes, resurface intersection • Osgood intersection and Greeley-Oakgreen intersection WILL NOT close at the same time

  12. Final Hwy 36 Intersections Looking East

  13. S. Frontage Road – Oakgreen to Osgood • Possible detours/temporary roads to access businesses/residences • Work: Resurface road, add turn lane, add curb & gutter, replace public utilities • Late summer to fall2014 (blue)

  14. Trail Construction • Work: Construct pedestrian/bicycle trails • Occurs as time allows, complete in fall 2014

  15. Other area county/city projects

  16. Wisconsin Approach Work Work occurs: March 2014-late summer 2016 Goal: Open WIS 64 at the same time as the new bridge

  17. 2014 Wisc. Approach Work • Grade from the bluff to County Road E • Build the WIS 35 overpass over the new WIS 64

  18. 2014-2017 Wisc. Approach Schedule

  19. The New St. Croix Crossing

  20. Bridge Superstructure • Timeline: Dec. 2013 to late-summer/early fall 2016 • Winter/Spring 2014 Impacts: Pile driving on the Minnesota shoreline and work on Pier 8 • Through May • 6 days per week -- 7 a.m.-7 p.m. • Goal: As much work done as possible while windows are closed

  21. Minnesota Land Piers Work Progress

  22. 2014 Bridge Construction • Build all river piers and land piers vertically (Piers 1-13)

  23. 2014 Bridge Construction • Begin casting segments – Approx. 1,000 • 656 extradosed segments • 330 approach segments • Two casting yard locations -- Gray Cloud Island and at the Hwy 36/95 interchange • Place first segment in fall 2014

  24. River Bridge Construction Staging

  25. Segment Lifter Example

  26. Construction Sequence

  27. Construction Sequence

  28. Construction Sequence

  29. Construction Sequence

  30. Construction Sequence

  31. Construction Sequence

  32. Construction Sequence

  33. Construction Sequence

  34. Construction Sequence

  35. Construction Sequence

  36. Construction Sequence

  37. Construction Sequence

  38. Construction Sequence

  39. Construction Sequence

  40. Construction Sequence

  41. Construction Sequence

  42. Construction Sequence

  43. Construction Sequence

  44. Construction Sequence

  45. Construction Sequence

  46. Construction Sequence

  47. Construction Sequence

  48. Construction Sequence

  49. Construction Sequence

  50. Construction Sequence