1 / 6

Fermilab E906 Schedule

Explore the history, current status, and future plans for the E906/Drell-Yan project at Fermilab, highlighting key milestones, financial considerations, and collaboration efforts.

sramey
Download Presentation

Fermilab E906 Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fermilab E906 Schedule Paul E. Reimer 20 June 2008

  2. E906/Drell-Yan History: • 1997: Completion of E866/NuSea. • 2001: Approved by Fermilab PAC —scheduling deferred until other fixed target experiments could also be ready to run. • 2005-06: Scheme to run E906/Drell-Yan with minimal impact on Neutrino production developed. No need for major fixed target run. • 2006: Fermilab PAC re-endorses wisdom of 2001 PAC. • 2007: DOE/Nuclear Physics begins funding spectrometer upgrade • 2007: Fermilab estimates cost (to Fermilab) to stage E906 at $1.5M in M&S plus manpower. Requests collaboration obtains additional funding to cover the M&S cost. • 2007-08: Additional institutes join collaboration (from Japan and Taiwan), taking responsibility for some of Fermilab’s tasks, and expect to provide additional money to Fermilab for E906/Drell-Yan infrastructure. • 2008: Spectrometer redesign promises reduces cost, savings in DOE/Nuclear Physics money may be transferred to Fermilab. Paul E. Reimer E906 Schedule

  3. Future Time Line Caveat:The crystal ball is murky. • July (early) 2008: Fermilab cost estimate complete • July (early) 2008: Geometry finalized • significant input from this meeting and follow up • July (late) 2008: Draft MOU circulated • August 2008 (early): MOU finalized • Fall 2008 to Spring 2009: Magnet and upstream beam line installation • Includes preparation of KTeV Hall for our use • Designed to give us access to KTeV Hall by Summer 2009 when significant student labor may be available. • Summer 2009: Spectrometer installation • January 2010: Start of run. • This is the earliest possible time • Fermilab is planning for a “long” shutdown in 2012, but not yet scheduled. We would like to be done by then. Caveat:This schedule has not been vetted with Fermilab. I have directly asked the question of when we might run, subject to funding scenario’s and expect an answer next week. Paul E. Reimer E906 Schedule

  4. Critical Path • Collaboration and Fermilab agreement on MOU (memorandum of understanding) • Must be finalized to spend (and obtain additional) DOE/Nuclear Physics Money and will outline our responsibilities. Collaboration • Station 1 MWPC design and fabrication • received DOE permission to spend design money • Station 3 Drift chamber design and fabrication • DAQ system • Station 3 and 4 Hodoscopes Fermilab • Beam line construction • Upstream must be phased with Tevatron downtime • Hall Preparation • Magnet Assembly Needed for our access to KTeV hall Paul E. Reimer E906 Schedule

  5. Realistic Schedule I need your input on • Resources that are needed for each task • $$$ Money is limited and availability corresponds to fiscal year boundries • Labor • Equipment (e.g. phototubes for hodoscopes, Fermilab wire winding facilities, DAQ) • Time estimates for each task • Task coordinator I will roll this information into a Gantt chart (MS Project) Paul E. Reimer E906 Schedule

  6. J-PARC Experiment Runs Expt. Funded Experiment Construction Fermilab MOU Publications 12 09 08 11 10 Funding • We have $400k which can be spent now • Possibility for some additional money in FY08 (now) • Additional funds in FY09 (but this could be limited by a continuing resolution which limits funds to DOE/NP) • Funds in FY10? (we would like to be done by then!!) • Money from Japan (RIKEN) for common infrastructure is likely not available before April 2009. Conclusion • We have a plan to get E906/Drell-Yan running! • Time may be tight • If we wait, money may slip away • Contributions and efforts from our new collaborators can make this happen! Paul E. Reimer E906 Schedule

More Related