BUILDING PERMIT PROCESSING. RATIONALE ( Lease Agreement, article on Miscellaneous – Improvements). “ The LESSEE shall not make any structural changes, alterations, additions or improvements on the Leased Properties without the prior written consent of the LESSOR… ”. TYPES OF PERMIT.
E N D
RATIONALE(Lease Agreement, article on Miscellaneous – Improvements) “ The LESSEE shall not make any structural changes, alterations, additions or improvements on the Leased Properties without the prior written consent of the LESSOR…”
TYPES OF PERMIT • New Construction/Renovation Permit • Demolition Permit • Excavation, Ground Preparation or Soil Investigation Permit • Fencing Permit • Repair/Repainting Permit • Occupancy Permit
PRE-REQUISITE TO ISSUANCE OF BUILDING PERMIT • Contract of Lease/Authority to Construct •Zoning and Land Use Clearance from P.D.O. •Compliance to Ecology Center’s Environmental Requirements • Compliance to Technical Requirements from other Departments
EXEMPTIONS • Sheds, children’s playhouses and the like, not exceeding 6 sq.m. • Open terraces or patios not exceeding 20 sq.m. • Installation of window grilles • Replacement of deteriorated roofing sheets, tiles, gutters, etc. • Repair of any interior partition not involving addition or alteration • Repair and replacement of plumbing and electrical line and fixtures
Application of Permit Building Permit Section Project Development Division Engineering Department Rm. 220, Bldg. 255 Barryman Road, SBFZ Tel. No. 252 4015
START Submit Documents to Eng’g Dept. Applicant Housing – SBIP Construction? Submit to LADD Housing Office / SBDMC Eng’g. Applicant No Yes 1
Complete ? Return Documents To Applicant Engineering Department END 1 Yes 2 No
Receive Documents Engineering Department Recording Engineering Department 2 3
Review Plans & Documents Engineering Department Ecology Center Fire Department Utilities Department Land & Asset Devt. Dept. Public Health & Safety Dept. Subic Water. Co. Planning & Development Office Law Enforcement Department Subic Telecom Coastal Petroleum Port Engineering 3 4
Complied ? Summarize Findings Write to Locator Engineering Department END 4 Yes 5 No
Building Permit Fee Assessment Engineering Department D.A. ‘s Approval? 5 No 6
Summarize Findings Write to Locator Engineering Department END 6
Building Permit Fee Assessment Engineering Department D.A. ‘s Approval? 5 Yes 7 No 6
Payment of Building Permit Fee Treasury Department Release Building Permit / Recording Engineering Department END 7
Time Frame 15 DAYS