2011-12 winter shutdown planning A.Tauro 6-1-2012 ALICE 2011-12 winter shutdown schedule - A.Tauro
V0.4 2011-12 winter shutdown EMC • Shielding TRD Shielding Open L3 Close L3 Beam off: Dec 8th at 6:00 AM Beam on: Mar 7th at 18:00 PM TC meeting - A.Tauro
UX25 access restrictions Open L3 Close L3 Access restrictions: Removal/installation of shielding (restriction includes RB24 triplets) • PX24 blocks: no access CR5 and UX25 • PX24 beams (35t): no access CR1-5, Expo, and UX-25 • All other blocks: no access to UX-25 (or 1-2 teams max, not on A-side) TRD insertion: no access to MNF and L3 AUG test (Arrêt Urgence General – General Emergency Stop) – no access UX25 DSO test (Department Safety Officer) – no access UX25 No access SX2 during manipulation of blocks in SX2 (except ACR and WRs) To be confirmed TC meeting - A.Tauro
L3 and MNF access restrictions Open L3 Close L3 To be confirmed • Wks 49-50 and 7: access in normal hours (e.g. TPC) to be coordinated with TC • Wks 1-2: no access inside L3 during TRD SMs insertion • When moving from low-beta to insertion platform: no access to MNF • When inserting the module: no access L3 and MNF • Watcher needed in wks 49-50 and from wk 6 onwards TC meeting - A.Tauro
EN-HE • 8th Dec (9:30): reinstall crane (PR-774) electronics • 8th Dec (AM): load test cavern cranes (20t) • 30th Jan. UX25 crane inspection by Brunnhuber • Wk 8: test UJ22 jig + annual maintenance P2 cranes EN-HE-LM • 14th Dec: maintenance lift CR1-4 • Lift stopped whole day (7:00 – 16:00) • Cavern lift has to be stopped as well for one day. Date tbc ALICE 2011-12 winter shutdown schedule - A.Tauro
TE-VSC • 8th and 9th Dec: close MNF valve and venting central beampipe • Feb 1st– 23rd: pump down central beampipe ALICE 2011-12 winter shutdown schedule - A.Tauro
GS-ASE • Week 52: evacuation test • Jan. 5th – 13th: RAMSES firmware upgrade • Jan. 9th: red phone maintenance • Jan. 20th and 26th: test fire detection • Week 5: sniffer maintenance • Week 6: maintenance gas detection (UX, CR5) • Feb. 21st: maintenance PAD/MAD • Guard will be provided by GS in order not to interfere with cavern access ALICE 2011-12 winter shutdown schedule - A.Tauro
EN-CV-OP – Dec • 7th Dec at 18:00-22:00: adjustment chilled water flow in the cavern + lower L3-Dipole cooling settings • Will affect all cooling plants • Keep as many detectors on till the 8th (DCS shutdown), in order to check that regulation works (EN-CV-DC side) • Keep L3 and Dipole till the end of the test • Week 50: rinsing of mixed water in UX25 cavern (Philippe) • Refilling in parallel will not affect ALICE cooling • End wk 50 (16th Dec): test of Dipole flooding alarm • Need access to Dipole (Philippe) ALICE 2011-12 winter shutdown schedule - A.Tauro
EN-CV-OP – Jan/Feb • Tue 2nd and Wed 3rd Jan: Maintenance ITS (old) ventilator in CR5 • Thu 5th and Fri 6th Jan:maintenance PMD-MTG-MTK ventilation units • Fri 6th Jan: stop chilled water (SU2) • Therefore stop mixed water (cavern, CRs) • Switch tap water into CRs • Week 2: • Cleaning cooling towers (Mon to Thu) • Maintenance L3 injection and UX25 extraction/injection units. Test of alarms • New motor L3 ventilation (date tbc) • Modification of chilled water pipe for L3 jacket (Mon) • Maintenance mixed water pumps PX24 (Mon-Wed) and UW25 (Wed-Thu) • Preparation services new ITS dehumidifier • Consolidation of automatic switchover to tap water into CRs • Week 3: • Restart chilled & mixed water (around Wed, tbc) • Maintenance L3 extraction unit. Test of alarms • Maintenance ventilation unit SG2 (Mon-Tue) will cut Ar/H2 ALICE 2011-12 winter shutdown schedule - A.Tauro
EN-CV-OP • Repair leak FB pipe: • 23rd Jan • Fernando compensatory measures • Removal unused FB pipe (I-side): • 24th-25th Jan • Need nacelle ALICE 2011-12 winter shutdown schedule - A.Tauro
EN-EL 1/2 • 13/12: Test general secours: stop general services for 10’ • Will affect all general services, also at P2. The UPSes for DAQ and DCS/HLT will bridge the power cut (assuming they manage to repair the DCS/HLT one on 8.12...). Also rack power (CRs and UX) will not be affected. • However all 'wall outlets', WR of the ACR, offices, meeting room, SXL2, coffee machine will be affected... Also the non ups part of the cooling plants as well as the gas system will be affected… • 17/12: Test auto-transfert: • 1.5 days to configure + 1 day test • No impact on experiments • Wed 18th Jan: maintenance power transformers: • Will cut EXD1/2X for 3h cut power to CRs (normal network) • Will cut ITS ventilator and HMPID rack in CR5 • Test AUG P2: Fri Jan 20th– No access UX25 • Major electrical perturbation affecting P2 for whole day ALICE 2011-12 winter shutdown schedule - A.Tauro
EN-EL 2/2 • Consolidation 48V network (after incident 11th Jan 2011) • 1 day no access to UX25 Feb 17th (tbc, K.Foraz) • Maintenance power transformer EMT306/2X • Feb 17th 6:00 to 10:00 • Will stop UX25 air extraction and injection (4h) –No access UX25 from 6:00 to 10:00 ALICE 2011-12 winter shutdown schedule - A.Tauro
EN-CV-BE • New ITS dehumidifier unit in SX2 • Electrical control cubicle during week 2 • Power cubicle : delivery week 4 • Cabling : week 4/5 • Start-up and commissioning : week 6 /7 ALICE 2011-12 winter shutdown schedule - A.Tauro
EN-CV-DC • RP sampling: Dec 8th • TRD. Periodic maintenance + replacement chilled water valve + preventive replacement pump + cleaning vacuum pump: plant stopped 2 days on Jan 5th and 6th • SPD. Periodic maintenance + put entire plant on UPS: plant stopped 1 day on Jan 6th • TOF-PHOS-EMC-SPD. Installation PHOS circulator+ replacement flowmeter + periodic maintenance: plant stopped from 9th to 17th Jan • TPC. Periodic maintenance + preventive replacement pump + include heaters in supervision + cleaning vacuum pump: pant stopped from 18th to 20th Jan • HMPID. Periodic maintenance + preventive replacement pump: plant stopped 2 days on Jan 23rd and 24th • TPC RR. Periodic maintenance + install new filters: plant stopped from Jan 25th to Feb 2nd • SDD-SSD. Periodic maintenance + replacement pump: plant stopped from 3rd to 9th Feb ALICE 2011-12 winter shutdown schedule - A.Tauro
BE-ABP-SU (survey) • Week 50 (Sat-Sun): with L3 doors open: • Zero measurement (SF, TPC feet, MNF valve, MNF) • Low Beta network update • C-side photogrammetry (EMCal) • Weeks 1-2: after each TRD insertion, requiring ½ day on low-beta: • MNF valve and MNF • Week 4: survey MTG • Week 5: at the end of TRD and EMCal, requiring three full days with both doors open: • TRD modules, CAL frame photogrammetry, MNF valve, MNF, SF deformation, TPC feet • Week 6:V0-FMD1 (Mon) and MTK ST1-2 (Wed-Fri) • Week 7:no access (reserve) • Weeks 9-10:survey MTK ST3-4-5 and PMD ALICE 2011-12 winter shutdown schedule - A.Tauro
DAQ • DAQ shutdown 21st Dec mid-day • DAQ start after cooling and power interventions, end wk 3 • Arrangements for individual LDCs can be organized (send a mail to alice-datesupport@cern.ch) ALICE 2011-12 winter shutdown schedule - A.Tauro
DCS Week 49 • Dec. 8 morning: shutdown all DCS for UPS repair; restart a.s.a.p. (afternoon) • Profit from DCS stop to make backup ! • Start (hardware) installation of new DCS cluster Week 50 • Dec. 12–14: Operating system and PVSS upgrade • Reboots required, coordinated with detectors • Dec. 15: New framework available for detectors • Detectors to validate functionality with new software Week 51-52-01 • Preparation of new DCS cluster • DCS available during CERN End-of-Year closure • with usual access limitations and best effort support Week 02-03-04 • New DCS cluster available for detectors • Expect all detectors to run on new cluster by week 5 ALICE 2011-12 winter shutdown schedule - A.Tauro
TPC • Take out capacitors on all A/C ROC ALICE 2011-12 winter shutdown schedule - A.Tauro
TPC heat screen • Check the loops for the thermal screen in week 6 (there was a leak) • We will need: • access to the TRD cooling plant • access to C side and A side of TPC • access to the miniframe and PP0 • Since the pipes are on the outside of the miniframe we would probably need a nacelle. ALICE 2011-12 winter shutdown schedule - A.Tauro
TPC sectors 11 to 15 • Week 49: • Thu 8/12: displace FMD2 box. The box can be reinstalled anytime (at latest in week 5) • TPC A-14/15 (4 days anytime) • Week 3: move PMD to parking position (see next slide) • Week 4: • Mon 23/1 AM: disconnect and displace SPD box • Mon 23/1 PM: disconnect and displace SSD box • Tue-Fri: TPC A-11/12 (4 days) • Sat: put back and test SSD box • Week 5: • Mon 30/1: put back and test SPD box • Tue: move V0-FMD1 to parking position (PMD already in parking position) • Wed-Fri: TPC A-13 (2 and 1/2 days) + FMD2 survey • Sat: move back and test V0-FMD1 • Week 6: • Mon 6/2: survey of V0-FMD1 ALICE 2011-12 winter shutdown schedule - A.Tauro
PMD • Thu 19th Jan: PMD moves to Parking Position • Week 4 - 6: PMD Maintenance • Replacing some of the modules which are having problem • Replacing some of the FEE Chains • Need cooling for the DAQ (Crocus) so that we can check the health of the modules and FEE chains. • Week 7 (after 17:00) and 8: Access to Crocus Crate for DAQ • Week 9 -10: PMD Moves back to Final Position ALICE 2011-12 winter shutdown schedule - A.Tauro
T0 • Investigation of the problem with lasersystem (laser, attenuator, optical splitters, optical cables) • Rack 018,019, start from ~16 January • Miniframe (from Feb.7th) • Upgrade of electronics and check of spare modules • Rack 018,019, start from ~16 January ALICE 2011-12 winter shutdown schedule - A.Tauro
TPC laser • Annual laser maintenance, 1-2 days. Needs normal power and cooling • Open mirror box below TPC sector A13 (bottom below TPC endplate) and possibly replace camera or mirror. 1-2 days. I want to do this because a weak picture from this mirror/camera makes C-side alignment difficult. Best done with L3 doors open. I believe access between the TOF and TPC should be OK. I need to be able to run the laser, so we need to mount the long laser pipe temporarily after opening of L3 doors. ALICE 2011-12 winter shutdown schedule - A.Tauro
TRD • 3 supermodules installation, cabling, commissioning (L3 access, A & C sides etc) • Arrival at CERN of Bernd & Co on 2nd Jan. around noon • Insertion sequence: 6-2-3 • Possible to have transport on Sun.8th Jan? • C19 power installation -> we will ask DCS • C16-19 Netgear switch rearrangement • I08/O08 Netgear switch rearrangement • DAQ upgrade (discussion on going between Joerg and DAQ group) • Pretriggerbackup PSU installation and LV cable rearrangements (I/O rack and C-side in L3) • BKF LV protection panel replacement (C-side in L3) • Cooling valves replacement for 10 sectors, C side (if necessary, ask Ana to judge) (C-side in L3) • Moving back pressure sensors from TPC TS to TRD (C-side in L3) • GTU optical fiber installation (Stefan) (C16,17,18 racks) • CR4 HV rearrangement for new super-modules ALICE 2011-12 winter shutdown schedule - A.Tauro
SPD • Disconnect pipes in front of L3 door: 14/12 (after 17:00) • New inox pipes in front of L3 door: from 14 to 17/12 (after 17:00) • Week 51 (half day): drill filter in PP3 (access PP4) + connect cleaning machine ALICE 2011-12 winter shutdown schedule - A.Tauro
EMC • 15/12 PM: delivery new nose (SXL2) • 12/1 (PM): delivery 2 SMs (SXL2) (not tested afterwards) • Nantes team: • Monday 16/1 PM: travel to CERN • 17-18-19/1: modification new nose in SXL2 + cavern preparation (insertion SM into rotator if possible) • Friday 20/1 PM: travel to Nantes • Monday 23/1 PM: travel to CERN • 24-25-26/1: insertion • Friday 27/1 PM: travel to Nantes ALICE 2011-12 winter shutdown schedule - A.Tauro
PHOS • As from Dec 8th (PM): • Fix condensation problem on pipes and on top of detector • New redundant power supply for crystal cooling unit • Flowmeter crystal cooling unit (tbc) • 2 new T sensors inside L3 • Replace RCU_0 in module_3 • Connect crystal plant and LVPS to FB water during cooling stoppage: • E.g. on Jan 5th ALICE 2011-12 winter shutdown schedule - A.Tauro
MTK • Repair bus bars on slats: ST4, ST5 and ST3 (only limited to the ones accessible) • Week 50 • Week 2 to week 9 • Change one quadrant in ST2 (3 Right Bottom); • Week 4 (Monday and/or Tuesday) • Connection check in ST1 (without opening); • January: no day fixed yet… ALICE 2011-12 winter shutdown schedule - A.Tauro
MTG • Maintenance Front-end Electronics, mostly spare installation: • 19th to 21st Dec. Nacelle needed and green fences must be dismantled • Check on RPC (MTR21-OUT) for gas tightness, eventual dismounting and eventual changing • Week 3. Nacelle needed • Survey of 2 half-planes (MT12-IN and MT12-OUT) including measurements withtheodolite and photogrammetry, survey of the other 6 half-planes with only theodolite measurements • Week 5. Nacelle needed • SAA3 Shielding - MTR in closed position • Week 6(tbc) - can some concurrent activity in the MTR be carried out (i.e. regional electronics)? • General global check • One week (tbc) ALICE 2011-12 winter shutdown schedule - A.Tauro
ZDC • Move detectors by 1.36m towards IP to solve the problem of collimator shadow ALICE 2011-12 winter shutdown schedule - A.Tauro
Other activities • Reinstall ADA (wk6) • SAA3 extension (February) • Pull cable DSS-SPD cooling plant • Modification BBF (EMCal access) • Install C-side ladder + trap • Picture ALICE (A.Saba) • Week 5 (Thu-Sat) • Replacement CR3 racks and removal air conditioning CR2-3-4 • From week 4 (tbc from Dominique: Cegelec) • Installation accelerometers • Test Dipole bus bars (2h, Pascal) with IR camera. Tbs in February • Need to remove plexi protection ALICE 2011-12 winter shutdown schedule - A.Tauro
Visits - Dec • VIP: StjepanMatin from 24Hours newspaper • 9th Dec. (ACR-Exhibition. 10:30 – 11:30). Resp.: S.Tesauri • Private visit. 7 people • 11th Dec. Resp.: P.Jacobs • Private visit. 4 people • 12thDec. Resp.: N.Valls • ~30 teachers from Czech Republic • 16th Dec. (PM). Resp.: K.Safarik • Private visit. 7 people • 17th Dec. (17:00). Resp.: C.Bortolin • 50 students from the University of Bologna Chemistry Department • 17th Dec. Resp.: R.Nania • Private visit. 2 people • 19thDec. (17:00). Resp.: A.Tauro • VIP: Kim Steele, New York Times Review • 21st Dec. Resp.: D.Hatzifotiadou • Private visit. 6 people • 21st Dec. Resp.: T.Kugathasan ALICE 2011-12 winter shutdown schedule - A.Tauro
Visits – Jan 1/4 • Private visit (3 people) • 5thJan. (15:00). Resp.: T.Morhardt • Private visit (2 people) • 7th Jan. Resp.: J.Wessels • Hungarian Student Group (25 people) • 11th January (9:00 to 10:00). Resp.: P.Levai • TI operators • 11th Jan. (14:00). Resp.: A.Augustinus • Private visit (1 people) • 12th Jan. (10:00). Resp.: C.Cheshkov • 2nd High School of Kozani, Greece. 50 students (not underground) • 12th Jan. Resp.: D.Hatzifotiadou • Steve Elkins (documentary film-maker) + his video team • 12th Jan. at 10:00. Resp.:D.Hatzifotiadou • Hungarian Student Group (25 people) • 13th Jan. (9:00 to 10:00). Resp.: P.Levai • Private visit (3 people) • 13thJan. (16:00). Resp.: N. van der Kolk • School visit (25 people) • 14th Jan. (13:30 – 15:00). Resp.: W.Riegler • Private visit (6 people) • 14th Jan. (14:15). Resp.: C.Bortolin • Private visit (3 people) • 14th Jan. (16:00). Resp.: D.DeGruttula ALICE 2011-12 winter shutdown schedule - A.Tauro
Visits – Jan 2/4 • Private visit (7 people) • 15th Jan. Resp.: C.Nygaard • Visit of NRF (National Research Foundation of Korea) people(6 visitors) • 16th Jan. (10:00). Resp. Y.W.Baek • VIP: Delegation (10 persons). President of the French Centre national de la recherchescientifique (CNRS) • 16th Jan. (14:30). Resp.: Y.Schutz • Private visit (2 people) • 16thJan. Resp.: P.Chochula • Private visit (1 people) • 17th Jan. (lunch time). Resp.: P.Chochula • 5 people from DELL • 18thJan. (10:00). Resp.: P.Chochula • 1 person from Scientific American • 18th Jan. (13:30). Resp. D.Hatzifotiadou • Private visit (2 people) • 18thJan. (lunch time). Resp.: P.Chochula • Group of 20 students from a high school in Utrecht, the Netherlands • 18th Jan (14:00). Resp. N. van der Kolk • Group of Italian students (42 students + 4 teachers) • 19th Jan (9:45). Resp.: C.Bortolin • Private visit (2 people) • 18th (after 16:00) or 19thJan. (PM). Resp.: J.Schukraft ALICE 2011-12 winter shutdown schedule - A.Tauro
Visits – Jan 3/4 • German officials from Frankfurt university (~30 persons) • 20th Jan (after 16:00). Resp. V.Linderstruth • Private visit (6 people) • 20th Jan. (after 17:00). Resp.: R.Turrisi • Private visit (5 people) • 20th Jan. (after 18:00). Resp.: F. Bock • Private visit 2 x 15 people (GSI / ALICE members + their partners) • 21st and 22nd Jan. Resp.: J.Thaeder • Students from Nyon (22 people) • 23th Jan. (9:00 – 11:30). Resp.: C.H.Denarie • Private visit (2 people) • 23rd Jan. Resp.: J.Wessels • Filming crew (2 people) • 24th Jan. Resp.: D.Hatzifotiadou • Private visit (30 people) • 25th Jan. (17:00). Resp.: K.Schweda • Group of 46 students from Trieste • 26th Jan. Resp.: M.Venaruzzo • VIP: Members of the Comitato per ilProgettoCulturale (IT) • 26th Jan. (12:15). Resp.: L.Pedroso • Group of 40 students + 4 teachers from Cagliari • 27th Jan. (9:00). Resp.: C.Cicalo ALICE 2011-12 winter shutdown schedule - A.Tauro
Visits – Jan 4/4 • German School Geneva, 9th grade, i.e. 14-15 years old, 15 pupils plus teacher • 30th Jan. Resp.: R.Renfordt • School visit (15 people) • 30th Jan. (10:00 – 11:00). Resp.: W.Riegler ALICE 2011-12 winter shutdown schedule - A.Tauro
Visits –Feb • Visit from the Red Bulletin – which is the ‘Red Bull Journal’ • 1st Feb. (14:00). Resp. W.Riegler • 50 students from university of Tübingen • 2nd Feb. Resp.: H-R.Schmidt • Private visit 10 people • 5th or 11th or 12th Feb. Resp.: S.Boele’ • School from Nyon (20 students) • 6th Feb. (AM). Resp. C.H.Denarie • 16 students from German school in Geneva • 7th and 9th Feb. Resp.: R.Renfordt • Visit of danish high school class (1 teacher and 12 students) • 9th Feb. (17:00). Resp. C.Søgaard • Electronic lead engineer from Sun Microsystems Norway • 10th Feb. (17:00). Resp. B.Skaali • Vice-Chancellor of Birmingham University and 7 senior figures from industry • 15th Feb. (12:00 to 13:00). Resp.: D.Evans • Group of 38 students + 4 teachers from Cagliari • 21st Feb. Resp.: C.Cicalo • 50 students from High-school LiceoScientifico "G. Salvemini" from Bari • 27th or 28th Feb. Resp.: V.Manzari • Two visitors from Mexican TV (Channel 22) • 28th or 29th February. Resp.: G.Herrera Corral ALICE 2011-12 winter shutdown schedule - A.Tauro
AOB • As from now ADI replaced by IMPACT • Please do not submit anymore ADI requests • ADI no longer used • IMPACT is the new CERN wide tool • See Fernando’s tutorial ALICE 2011-12 winter shutdown schedule - A.Tauro