An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Reserve Adequacy AssessmentJanuary 14, 2004 Joseph Mercer Supervisor ISO-NE Operations Forecast

  2. Current RAA Commitment • Initial RAA – Commit to meet • Forecast Demand plus 10 Min Reserve plus 30 Min Reserve plus Replacement Reserve plus surplus of 400 MW w/SAR, 700 MW w/o SAR. • RAA Updates – Commit to meet • After morning generator start-up cycle, (typically 0800), target surplus is reduced to 0 MW. • Commitment Objective - minimize following costs: • Generator Start-up, No load and cost to operate at EcMin • All generator start-up orders (DAM or RAA) issued/verified by ISO by 2200

  3. Cancelled Start-Ups • March 1, 2003 – August 31, 2003 • ISO-NE cancelled start-ups on 21 days • Cost of cancellations ($17,173) • September 1, 2003 – December 31, 2003 • ISO-NE cancelled start-ups on 30 days • Cost of cancellations ($17,252)

  4. “Just in Time” Commitment • Initial RAA and updates • Capacity requirements are same as current practice • Commitment Objective • Commit units with shorter start-up and notification times (<6 hrs) • Generator with longer times will not be committed, unless there is insufficient capacity available from shorter lead time units. • Generator Start-up, No load and cost to operate at EcMin • DAM generator start-ups verified by 2200 • If applicable, DAM scheduled units should call in start-up profile to the Forecast Office during Re-Offer period • RAA start-ups issued “Just in Time” to meet generator submitted Notification and Start Times. • Have identified software changes, new reports, affected processes.

  5. “JIT Pros and Cons Pros • Reduce ISO-NE intervention in the Energy Market by delaying RAA commitment decisions until a few hours prior to real-time peak • Reduce or eliminate canceled start-up and related costs • Provide price volatility in Real-time when short lead time units are order on-line. • Reward generators for providing flexible operating characteristics. • Reduce calls to marginal generators (Order on, then cancel) Cons • JIT commitment may not always meet the current Commitment Objective should the units be called to operate in Real-time. • May need changes to Manual 11