An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Store Summary Tevatron Coordinator - FNAL

  2. Numbers for the week Tevatron Coordinator - FNAL

  3. Lum for the week Tevatron Coordinator - FNAL

  4. Integrated for the Week Tevatron Coordinator - FNAL

  5. Studies/Work Completed • BOS to work on system to increase pbar transverse emittance. (currently blowing up Emit at injection). • After Quench on Store 5843 parsed squeeze and redefined orbit, tunes and coupling. These are big changes. Tevatron Coordinator - FNAL

  6. Problems • Replaced regulator for T:VC43 after tripping during shot setup. • D17V separator spark (little loss of lum) • RF station trip during store. (little loss of lum) Tevatron Coordinator - FNAL

  7. Pbar Brightness Squeeze Quench Store 5843 Tevatron Coordinator - FNAL

  8. D0 Losses in Squeeze after Parse LMC4SM LMB1SD Tevatron Coordinator - FNAL

  9. Rough Results of Pbar Emit growth Used PBJ to increase Pbar emittance Store 5852 Store 5850 Tevatron Coordinator - FNAL