RUS Telecommunications Infrastructure Loan Program Engineering Updates Peter Aimable, Director Northern Division Telecommunications Program, RUS 2012 ACE RUS School and Symposium
Engineering Updates • Contract negotiations • Delays on fiber delivery • Contract rider • Time extensions on loans • Requesting advance of loan funds • Other issues • Q&As 2
Negotiations of Outside Plant Contracts • Negotiation – any form of purchasing or contracting other than sealed competitive bidding. Any contract awarded without using the sealed competitive bidding procedure is a negotiated contract • Sealed competitive bidding is the Norm • No competitive bids are required for OSP projects of $250,000 or less including labor and materials 3
Conditions for negotiating Outside Plant Contracts • Overall lack of contractors in geographic area • Short notice of completion of project (time element) • Evidence of poor bidding experience for small-dollar projects in the area • Availability of materials is critical, wherein only certain contractors have access to fiber materials on the necessary schedule • Lack of experienced contractors for specific types of project 4
Few Millions Few hundreds $250,000 5
Delays on fiber delivery • Proper planning – increase planning cycle • Negotiations –written RUS approval required • Supplement “A” method of providing fiber • RUS written approval is required • How will the purchase of the cables be funded initial? 6
Contract Rider • Required in all new contracts, contract amendments and subcontracts submitted to RUS for approval • Intended for clarification • Rider does not change or alter any existing legal rights or obligations in RUS standard contracts • Located on RUS website at www.rurdev.usda.gov/UP_ETPW_Forms.html 7
Issues with time extensions on loans • Long period of construction inactivity • No extensions on FFB guaranteed funds • One or two year extension may still be possible on some loans for extenuating circumstances but extensions are going away in the future • Extensions should be requested through Division Director with reasons and proposed draw down timeframe 8
How to receive an advance of loan funds quicker • File financial report requirements promptly • Submit completed Form 481 (FRS) • Use the latest instructions for completing form • Signed by an authorized official • Include invoices for Pre-loan Engineering and Operating Equipment (vehicle, work & test equip, etc.) • Include work order summary (Form 771/771a) with proper descriptions, signatures, and GFR initials 9
Other issues • Related party service (charges at cost or market value) • Disallowance on post-loan engineering services • List of materials 10