ONCODEATH Sensitization and resistant determinants of cancer cells to death receptor related therapies. Contract No: LSHC-CT-2006-037278 Kick off meeting Athens, 1 December 2006. Contract Details (1). Specific Targeted Research Projects Started date: 1 st November 2006 Duration: 36 months
E N D
ONCODEATHSensitization and resistant determinants of cancer cells to death receptor related therapies Contract No: LSHC-CT-2006-037278 Kick off meeting Athens, 1 December 2006
ContractDetails (1) • Specific Targeted Research Projects • Started date: 1st November 2006 • Duration: 36 months • Community financial contribution: 2,344,900.00€
Contract Details (2) • Reporting periods: • P1: From month 1 to month 12 • P2: From month 13 to month 24 • P3: From month 25 to the last month of the project • Reports submission: • P1 – period P1 & P3 – periods P2 + P3 • Within 45 days from the end of the reporting periods
Contract Details (3) • Community financial contribution: Paid to the coordinator on behalf of the contractors – Distributed as soon as possible • Payments: • Pre-financing: 938,108.00€ - within 45 days from the entry into force of the contract • Intermediate payments: • With an audit certificate: • Payment to settle the amounts justified and accepted • Intermediate pre-financing of 80% to the subsequent period and the next 6 months • Without an audit certificate: • Intermediate pre-financing of 80% to the subsequent period and the next 6 months within 45 days from the approval by the Commission of the reports – necessarynot less than 70% of a pre-financing has been used
Amendments • Necessary the identification of the nature and the details of the request • Submitted in writing only by the coordinator on behalf of the consortium • Approval or rejection between 45 days of its receipts
Consortium Agreement • Based on Model Consortium Agreement provided by relevant working-group of the EU • Main Subjects covered: • Organizational and Management Structure • Party’s responsibilities and authority • Confidentiality • Liabilities • Intellectual Property Rights Distributed for comments
Obligations • Forms A & A4 – signed and send until the end of December • Pre-financing paid until 15 of December 2006 (?) and distributed ASAP • Consortium Agreement signed and send until the end of December • Launching of project’s Web Site until ……