PMBoK Chapter 7. Sections 1-3: Standard Section 4: Math. Outline. Section 7.1: Note that this is first bubble in previous slide…. Section 7.2: Note that first input is output from previous slide. Section 7.3: Note that three inputs come from 7.1 and 7.2 outputs.
E N D
PMBoK Chapter 7 Sections 1-3: Standard Section 4: Math
Section 7.1: Note that this is first bubble in previous slide…
Section 7.2: Note that first input is output from previous slide.
Section 7.3: Note that three inputs come from 7.1 and 7.2 outputs.
Section 7.4: Earned Value Management (EVM) Methodology that combines scope, schedule, and resource measurements to assess project performance and progress (with a dozen acronyms). Example: A million dollar project is planned to be done in 16 months. After 8 months, the data is: • AC = $580,000 • PV = • EV = $430,000 • a) What are the BAC and what do the three items above mean? • b) Calculate and interpret the remaining eight earned value statistics.