1 / 25

CHAMONIX XV QRL installation and first experiences of operation

CHAMONIX XV QRL installation and first experiences of operation. G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in sections, AT/VAC, AB/CO, TS/IC, TS/SU groups for their support and collaboration 2006.01.25. Contents. QRL layout Installation

ulric
Download Presentation

CHAMONIX XV QRL installation and first experiences of operation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CHAMONIX XVQRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in sections, AT/VAC, AB/CO, TS/IC, TS/SU groups for their support and collaboration 2006.01.25

  2. Contents • QRL layout • Installation • Main features • Present status • Schedule • Operation  Reception tests • Schedule • Main results • Conclusions 2

  3. QRL layout • QRL is a continuous cryostat of ~3.2 km length • no header (4 or 5) sectorisation 9 vacuum sub-sectors (A…I) •  vacuum insulation separate from machine Tested part is marked in blue Vacuum sub-sector “A” A - A C F D G E H B • QRL elements in one sector • ~ 38 service modules • ~ 40 fixed point/vacuum barrier elements • ~ 235 straight pipe elements • ~ 10 steps/elbows • ~ 1-2 cryogenic extensions I 3

  4. QRL layout Sector 3-4 Pipe element Service module Sector 5-6 4

  5. QRL sector installation • Installation of ~ 700 external supports • Positioning of ~ 325 elements • Welding and testing of ~ 325 interconnections  > 2000 welds • ~ 180 “O” type interconnections (1 butt-weld per header) • ~ 75 “C” type interconnections (2 butt-welds per header) • ~ 70 “A” type Interconnections (3 welds per header) 5

  6. QRL sector installation Tool for He leak test • Overall installation: 6 teams • Installation by sub-sectors • Automatic welding for the inner headers • Nominal rate: 20 int./week • Achieved rate: 30 int./week • Manual welding of the external sleeves • Nominal rate: 20 int./week • Achieved rate: 35 int./week • NDT tests • Internal (video camera) and external visual control: 100% • Radiography tests: from 100 % to 10 % as a function of weld quality • Leak tightness tests: 100 % (each weld, each sub-sector, each sector) Head of the machine 6

  7. Status of the installation 7

  8. Schedule 8

  9. Reception tests • QRL tests: • Sector 7-8, sub-sectors A and B: about 700 m • Sector 8-1, full sector: about 3200 m • Tests • Pressure tests • Flushing of the circuits • Cooldown • Instrumentation commissioning • Heat inleak measurements • Warmup 9

  10. Reception test schedule 10

  11. Pressure test Sector 8-1 11

  12. Configuration for flushing and cool-down 12

  13. High-flow rate flushing with He New filter (8-1) Old filter (7-8, A-B) Original colour ! 13

  14. QRL layout for reception test 14

  15. Tests for the sector 8-1 15

  16. Cool-down Valve blockage by a “plastic film” coming from header B 16

  17. Thermometer validation Header C, SSA: 8 TT fully in accordance 17

  18. Heat inleak measurement B, C and D QB,C,D = (mD·hD+mB·hB) - mC·hC (indirect calculation of the mass-flow by using the heaters EH) E and F QEF = mF·(hFout-hFin) + mE ·(hEout-hEin) 18

  19. Results for headers E and F • Boundary conditions • Insulation vacuum in the main envelope: • 10-6 mbar (8-1) • 10-5 mbar (7-8) • Headers E and F: 50-75 K • Headers C, D and B: 8-15 K 19

  20. Results for headers C, B, D (sector 7-8, A and B) JC = jumper connection JR = junction region • - without JR and without JC ~ 0.25 W/m • JC ~ 50 W  4.2 W/JC • JR ~ 70 W  1 W/m Measurement cross-checked with independent refrigerator input 20

  21. Results for headers C, B, D (sector 8-1) QRL with JR and without JC • Boundary conditions • Insulation vacuum in the main envelope: 10-6 mbar • Headers E and F: 50-75 K • Headers C, D and B: 8-15 K Mass-flow cross-checked by using the valve opening Measurement cross-checked with independent refrigerator input 21

  22. Results for headers C, B, D (sector 8-1) • - without JR and without JC ~ 0.16 W/m • JC ~ 90 W  2.4 W/JC • JR ~ 35 W  0.4 W/m 22

  23. Temperatures of the vacuum jacket 23

  24. Conclusions 1/2 • Installation progresses well: • External support installation at 75 % • Element installation at 50 % • Installation in the sectors 3-4 and 5-6 (JR excluded) meets the target rates • At present the main concerns for the installation are: • delay for leak detection and repair • availability of singularities for the sector 1-2 (2 JR  18 elbows/steps) • installation of the QRL in UJ22 and UJ24 and possible interference with magnet transport: tooling for QRL installation shall allow the magnet transport • Pressure tests successfully performed for sectors 7-8 (A+B), 8-1 and 4-5 (without the JR) • Flushing of headers required and sufficient time shall be allocated 24

  25. Conclusions 2/2 • Cold reception tests performed for sectors 7-8 (A and B) and 8-1 • Successful thermo-mechanical validation of the QRL design • Thermometer accuracy of about +/- 50 mK, much better than specification (+/- 1 K for T> 6K) • Heat inleaks to 50-75 K (headers E and F) circuit within specification • For sector 7-8 (sub-sectors A and B) heat inleaks to 4-20 K (headers B, C and D) above specification. Possible causes identified: • Higher thermal shield temperature than expected • Higher insulation vacuum than nominal • Not nominal insulation vacuum in the jumpers: impact on the heat flux through MLI • For sector 8-1 heat inleaks to 4-20 K circuit are within specification • Important: Header B heat inleaks within the specification (QRL heat inleaks represents more than 95 % of the corresponding total budget) • Other QRL sectors cold tested with the cryo-magnets: still possibility to measure the heat inleaks to the headers only (at present no allocated time for this test) 25

More Related