270 likes | 399 Views
Introduction to Understanding Plans. 2006 Highways & Engineering Conference. Introduction. Know your plans White = preliminary/design phase Blue = final review phase (still taking comments) Ivory = final plans Types of plans Right of Way Utility Construction (focus of this presentation).
E N D
Introduction to Understanding Plans 2006 Highways & Engineering Conference
Introduction • Know your plans • White = preliminary/design phase • Blue = final review phase (still taking comments) • Ivory = final plans • Types of plans • Right of Way • Utility • Construction (focus of this presentation)
Title Sheet • Provides basic project information • Project number • Scope of project • Name of project • County • Length of project • Maps of project • Beginning and ending stationing and referencing points • Denotes any bridges within project limits
Title Sheet (cont.) • Basic project information (cont.) • Design and traffic data • Surfacing sources • Logo and designer • Source to find out more about the project • Control number • Best way to identify the project • Engineer’s approval • Scale • CSF-combination scale factor • Plans scale
Sheet 2 • Table of contents • Lists the contents of the project plans and the corresponding sheet numbers • Notes • Additional project specific information for the contractor and construction inspectors (i.e. basis of plan quantities)
Sheet 3Linear and Level Data • Shows the design centerline coordinate table and benchmark locations and elevations • Length of roadway • Length of bridges (if any) • Source data for bearing • Level datum source
Sheets 4 and 5 • Control Traverse Diagram • A visual layout of the surveyed control traverse for the project • Control Traverse Abstract • It lists the control point numbers and describes their physical location • Sheets 3, 4, and 5 contain the survey information that was established and used to design the project. And is the same information used by the field crews to build the project.
Typical Sections Sheet 6 • Typical sections are cross sections of the roadway and terrain at defined intervals • They include the following information • Type and thickness of material to be used to construct the roadway • Widths of finished driving surface and subgrade • Surfacing quantities • Cut and fill slope rates • Stations (from/to) where typical section applies • Identifies transition from a given typical to the next
Summary Sheets Sheets 9-15 • Summarize all quantities of work and/or materials required by the project • The contractor uses this information to prepare a cost estimate for bid • Summary sheets provide • Name of the item (i.e. pavement removal, curb, culverts, etc…) • Quantities required and the unit of measurement • Location where the product is to be used by station • Distance from the centerline (if applicable)
Detail Drawings Sheets 18-23 • Additional design details • This information is usually specific to the project and not contained in MDT’s standard detailed drawings (i.e. irrigation siphon, detours, etc…)
Mass Diagram Sheet 24 • Not all sets of plans have a mass diagram- only ones with earthwork projects • The mass diagram illustrates the volume and movement of earth needed to construct the roadbed (cut and full)
Plan Sheets • Contains the basic geometry of the road along with horizontal (left/right) and vertical (up/down) curve data • Are divided into two views • Plan view is as one looks at the roadway from above (on the upper half of the page) • Profile view is as one looks at the roadway from the side (on the lower half of the page)
Elements on Both Plan & Profile Views • Centerline • Stations • Callouts • Offsets
Centerline • The centerline is a solid notched line on plans depicting the center of the roadway • Each notch represents • 20 M (Metric) • 20 ft. (English) • C L
Stations • The measurement for distance and used for identifying specific locations on the project • Stationing is measured along the centerline • It does NOT usually start at 0+00.00- its starting point is dependent on historical projects
Stations (cont.) • A metric station = 100 M • An English station = 100 ft. • 17+70.05 = 1,770.05 meters • Stations are numbered left to right on the plans • Position left or right of centerline is determined as one faces the direction of increased station numbers
Callouts • Points on plans that provide more detail about a certain feature (i.e. pipe, power lines, etc…) Information included in callouts: • Station • Physical attributes • Shown on both the plan and profile view
Offsets • Location of items not directly on centerline • Described as left (LT) or right (RT) of centerline station
Plan View Sheet 34 • Horizontal alignment of the roadway • North/south directional arrow • Centerline curve data located by station on the plan-stationing is shown at the top of the view • Existing topography • Buildings, trees, rivers, etc.. • New right-of-way • Existing right-of-way easement • Culverts
Find the following NO (refer to sheet 2) • Are there any impacted wetlands? • Is there a core hole? • What type of utilities are shown? • How many horizontal curves are shown? • Are there any new culverts? YES Telephone & Fiber optic 3 NO- just a removal (refer to culvert summary-pgs. 12 & 13)
Profile View Sheet 34 • Shows the elevation view of the roadway centerline for the proposed and existing roadway • Stationing is shown at the bottom of the profile view (horizontal axis) • Elevations are shown on the left hand side of the profile view (vertical axis) • Vertical alignment data • Vertical curve data
Profile View (cont.) • Guardrail stations- new and remove • Approach locations- new and abandon • Includes public, private, commercial, and farm/field • Other details • Retaining walls • Sub-excavation • Geotextile • Bridge ends • Core locations with core data • Mail box turnouts
Find the following 70+02.98 • What station does the guardrail end at on the left? • What is the length of the vertical curve at station 70+20? • What is grade of the road between station 70+20 and 73+90? • At what station is core hole #5? 150 meters 2% 70+65.60
Other Parts of Plans • Some other sections of plans you may encounter • Signing plans • Bridge plans • Electrical plans • Cross sections • Wetland mitigation plans