1 / 15

VELO-meeting January 25, 2007

VELO-meeting January 25, 2007. Sub-projects: SX8-2.003 & SX8-2.004 connectorize cooling cables alignment procedure motion test bake out procedure turn over project D P-project VELO vacuum commissioning LHCb installation planning summary + timelines. clean up SX8-2.003&4.

whitney
Download Presentation

VELO-meeting January 25, 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. VELO-meetingJanuary 25, 2007 • Sub-projects: • SX8-2.003 & SX8-2.004 • connectorize cooling cables • alignment procedure • motion • test bake out procedure • turn over project • DP-project • VELO vacuum commissioning • LHCb installation planning • summary + timelines VELO sub-projects

  2. clean up SX8-2.003&4 Spaces 2.003 and 2.004 are future storage, repair and working places for the whole VELO + PU communities. With other people and parts/equipment approaching soon, our stuff needs to be reorganized/cleaned up. Estimated time: 0.5 manweek. VELO sub-projects

  3. Cabling • 22 Jan  16 Feb: • - pull long-distance (RB84  D3) analog cables by INEO • - “simultaneously” connectorize D3-side • 19 Feb  23 Feb: • - pull control cables (RB84  balcony) • 26 Feb  2 Mar: • - pull HV cables (RB84  D3) Cooling cables still need to be connectorized at both ends, i.e. RB84 and C3. Estimated time: 2*1 manweek. VELO sub-projects

  4. Alignment Centre Frame Fiducial Marks Alignment procedure uses 5 fiducial points on each side of center frame. However, these are soon not visible anymore due to the repeater crates, mounted on the detector hood. VELO sub-projects

  5. Solution: Install new alignment points above and below the existing ones. Watch out that the analog cable supporting frame is not in the way also. Estimated time: design: 1.5 mw construction: 1.5 mw implementation: 2*0.5 mw VELO sub-projects

  6. Motion • Increasing expertise with the system has revealed the • necessity to take a few additional safety measures. • Partly to be implemented in the PLC, partly in the PVSS application. • moving both XL and XR in the same direction from a position in • which XL=-XR, needs special precautions. • implement the possibility to stop the stepper motor when really • necessary (moving wrong way based on pot. meters, one side not • moving at all, etc.) Estimated time: thinking: 2 mw implementation: 2 mw testing: 2*1 mw VELO sub-projects

  7. Test bake-out procedure Bake-out procedure of rf-boxes has to be commissioned: regulation of lamps, temperature interlock, etc. Estimated time: preparation: 1 mw implementation: 2*1 mw VELO sub-projects

  8. Turn over project Rotation of the detector half is a delicate, not yet well-established activity. Likely solution: Use 2 small cranes. Either powered by hand or electricity. Estimated time: preparation: 0.5 mw production of test tool: 0.5 mw ? testing: 2*0.2 mw VELO sub-projects

  9. DP project Dx [mm] Dp [mbar] (elastic) deflection: 0.3 mm @ 4 mbar 0.4 mm @ 5 mbar VELO sub-projects

  10. Dp=pbeam-pdet [mbar] evacuation foil hits sensors side VELO sub-projects

  11. Dp=pbeam-pdet [mbar] venting foil hits sensors side VELO sub-projects

  12. Possible remedy: change Dp-range and/or central Dp-value. Estimated time: preparation: 2*1 mw testing: 2*0.5 mw VELO sub-projects

  13. VELO vacuum commissioning • Unacceptable leak rate (10-5 mbar.l/s) of rf-boxes necessitates • additional tests + attempts to (temporary) fix the problem. • Present plan with VELO + part I of the beam pipe: • evacuate • bake rf-boxes @ 160 oC • vent ?? • evacuate ?? • determine leak rate • vent • seal “holes” with Varnish • evacuate • determine leak rate • Estimated time of NIKHEF-involvement: 2*2 mw VELO sub-projects

  14. LHCb installation schedule • Coming months lots of activities from RICH1, TT, VELO • (HV, LV, ECS, etc.) in the vicinity of the VELO. Need for • coordination, flexibility and mutual cooperation. • Jan 22  Mar 2: • Cabling (analog + control) around the VELO. • March + April: installation LV-distribution boxes, • HV-patch panels • April 5: • Start bake out + commissioning of the complete • LHCb beam pipe. VELO sub-projects

  15. Summary VELO sub-projects

More Related