An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. San Joaquin Delta College Measure L Bond Program March 12, 2013

  2. Danner Safety (Air Quality Study) Overview: The project consists of investigating and evaluating ways to improve the air quality by the improvement of air circulation within the occupied spaces adjacent to the loading docks.

  3. Danner Safety (Air Quality Study) • Where: Project Location

  4. Danner Safety (Air Quality Study) Original Project Information: Area: N/A g.s.f. Contract Award: June 2013 Complete Construction: September 2013 Architect: Dougherty & Dougherty Contractor: To be determined

  5. Danner Safety (Air Quality Study) Current Project Status: Budget: On Budget Schedule: On Schedule Change Orders: N/A General Problems: None Safety Problems: None

  6. Danner Safety (Air Quality Study) Project Budget and Expenditures

  7. Danner Safety (Air Quality Study) • When: Project Schedule

  8. Forum Classroom Renovations • Overview: • The project consists of renovating three classrooms within the Forum Building to include meeting accessibility compliance codes, carpet and seating replacement, and upgrading the finishes throughout the classrooms.

  9. Forum Classroom Renovations • Where: Project Location

  10. Forum Classroom Renovations Original Project Information: Area: 5,600 g.s.f. Contract Award: April 2013 Complete Construction: August 2013 Architect: Lionakis Contractor: To be determined

  11. Forum Classroom Renovations Current Project Status: Budget: On Budget Schedule: On Schedule Change Orders: N/A General Problems: None Safety Problems: None

  12. Forum Classroom Renovations Budget and Expenditure Report:

  13. Forum Classroom Renovations • When: Project Schedule

  14. Holt Building/Budd Shop Renovations Overview: This project scope consists of general building renovations to the shops and classrooms in the Holt and Budd buildings. This consists of upgrades to meet accessibility compliance and fire codes and updates to the existing utility infrastructure to current District standards.

  15. Holt Building/Budd Shop Renovations • Where: Project Location

  16. Holt Building/Budd Shop Renovations Original Project Information: Area: 52,000 g.s.f. Contract Award: August 2014 Complete Construction: December 2015 Architect: To be determined Contractor: To be determined

  17. Holt Building/Budd Shop Renovations Current Project Status: Budget: On Budget Schedule: Assessment Change Orders: N/A General Problems: None Safety Problems: None

  18. Holt Building/Budd Shop Renovations Project Budget and Expenditures

  19. Holt Building/Budd Shop Renovations • When: Project Schedule

  20. Math and Science (New Construction) Overview: The construction consists of a new three story math/science complex including a 70,000 sf laboratory core, with primarily dry labs on the first floor, wet Biology labs on the second floor, and chemistry labs on the third floor. There is 20,000 sf of office space and 20,000 sf of classrooms on each floor dedicated to each discipline, primarily in separate zones. The labs wrap around a central service core consisting of tech offices, lab preparation rooms, and lab storage rooms. Students will enter the labs from the opposite side of the central service core providing safe separation of students and chemicals. Student break-out spaces, computer labs, and a resource center for studying and tutorial sessions will be provided. During the programming and planning effort the building was sited north of the existing Shima Center. This location was chosen due to its proximity to public and student parking for easy access to the proposed future Planetarium and the Math/Science building, as well as a separate service drive for easy access to the labs. The new building replaces an outdated 92,000 sf science building currently in use. The exterior building’s form, materials and colors reflect a modern interpretation of the “Village” character of the existing campus buildings. This is a State funded project with a 50% match with local funds.

  21. Math and Science (New Construction) • Where: Project Location

  22. Math and Science (New Construction) Original Project Information: Area: 110,000 g.s.f. Contract Award: January 2010 Complete Construction: March 2013 Architect: tBP Contractor: Taisei

  23. Math and Science (New Construction) Current Project Status: Budget: On Budget. Project is 50% state funded. Schedule: Revised Completion Date for Phase I is March 2013 Change Orders: 25 General Problems: N/A Safety Problems: N/A

  24. Math and Science (New Construction) Project Budget and Expenditures

  25. Math and Science (New Construction) • When: Project Schedule Math and Science

  26. Manteca Barn, Shade, and Fence Overview: The project entails the new construction of a pre-engineered metal building to serve as a barn, laboratory, & teaching facility. The new barn will have a canopy and new perimeter fencing enclosing the rear of the structure to facilitate the herding of livestock.

  27. Manteca Barn, Shade, and Fence • Where: Project Location

  28. Manteca Barn, Shade, and Fence Original Project Information: Area: 3600 g.s.f. Contract Award: August 2013 Complete Construction: March 2014 Architect: ANOVA Contractor: To be determined

  29. Manteca Barn, Shade, and Fence Current Project Status: Budget: On Budget Schedule: Project has been put on hold Change Orders: N/A General Problems: None Safety Problems: None

  30. Manteca Barn, Shade, and Fence Project Budget and Expenditures

  31. Manteca Barn, Shade, and Fence • When: Project Schedule

  32. ShimaHeavy Equipment / Diesel Expansion • Overview: • This project provides for a modest expansion of the Shima Center in order to expand the heavy diesel engine, hydraulics and repair program, and to allow the auto program to expand in Holt. The expansion includes additional shop space, an exterior open air laboratory and a new diesel laboratory shop area.

  33. ShimaHeavy Equipment / Diesel Expansion • Where: Project Location

  34. ShimaHeavy Equipment / Diesel Expansion Original Project Information: Area: 12,000 g.s.f. Contract Award: November 2012 Complete Construction: January 2014 Architect: Lionakis Contractor: Seward L. Scheder

  35. ShimaHeavy Equipment / Diesel Expansion Current Project Status: Budget: On Budget Schedule: On Schedule Change Orders: N/A General Problems: None Safety Problems: None

  36. ShimaHeavy Equipment / Diesel Expansion Budget and Expenditure Report:

  37. ShimaHeavy Equipment / Diesel Expansion • When: Project Schedule

  38. Stockton Campus Restroom Renovations • Overview: • The scope will consist of renovating several restrooms on campus to meet current building codes and update fixtures to the District’s current standards. The restrooms scheduled for the renovation are contained within the following buildings: Administration, Atherton, Budd, Danner, Forum, Locke, and Shima.

  39. Stockton Campus Restroom Renovations • Where: Project Location

  40. Stockton Campus Restroom Renovations Original Project Information: Area: N/A g.s.f. Contract Award: April 2013 Complete Construction: September 2013 Architect: Lionakis Contractor: To be determined

  41. Stockton Campus Restroom Renovations Current Project Status: Budget: On Budget Schedule: Project Bidding Change Orders: N/A General Problems: None Safety Problems: None

  42. Stockton Campus Restroom Renovations Budget and Expenditure Report:

  43. Stockton Campus Restroom Renovations • When: Project Schedule

  44. Question and Answer March 12, 2013