San Joaquin Delta College Measure L Bond Program March 12, 2013. Danner Safety (Air Quality Study). Overview:
E N D
San Joaquin Delta College Measure L Bond Program March 12, 2013
Danner Safety (Air Quality Study) Overview: The project consists of investigating and evaluating ways to improve the air quality by the improvement of air circulation within the occupied spaces adjacent to the loading docks.
Danner Safety (Air Quality Study) • Where: Project Location
Danner Safety (Air Quality Study) Original Project Information: Area: N/A g.s.f. Contract Award: June 2013 Complete Construction: September 2013 Architect: Dougherty & Dougherty Contractor: To be determined
Danner Safety (Air Quality Study) Current Project Status: Budget: On Budget Schedule: On Schedule Change Orders: N/A General Problems: None Safety Problems: None
Danner Safety (Air Quality Study) Project Budget and Expenditures
Danner Safety (Air Quality Study) • When: Project Schedule
Forum Classroom Renovations • Overview: • The project consists of renovating three classrooms within the Forum Building to include meeting accessibility compliance codes, carpet and seating replacement, and upgrading the finishes throughout the classrooms.
Forum Classroom Renovations • Where: Project Location
Forum Classroom Renovations Original Project Information: Area: 5,600 g.s.f. Contract Award: April 2013 Complete Construction: August 2013 Architect: Lionakis Contractor: To be determined
Forum Classroom Renovations Current Project Status: Budget: On Budget Schedule: On Schedule Change Orders: N/A General Problems: None Safety Problems: None
Forum Classroom Renovations Budget and Expenditure Report:
Forum Classroom Renovations • When: Project Schedule
Holt Building/Budd Shop Renovations Overview: This project scope consists of general building renovations to the shops and classrooms in the Holt and Budd buildings. This consists of upgrades to meet accessibility compliance and fire codes and updates to the existing utility infrastructure to current District standards.
Holt Building/Budd Shop Renovations • Where: Project Location
Holt Building/Budd Shop Renovations Original Project Information: Area: 52,000 g.s.f. Contract Award: August 2014 Complete Construction: December 2015 Architect: To be determined Contractor: To be determined
Holt Building/Budd Shop Renovations Current Project Status: Budget: On Budget Schedule: Assessment Change Orders: N/A General Problems: None Safety Problems: None
Holt Building/Budd Shop Renovations Project Budget and Expenditures
Holt Building/Budd Shop Renovations • When: Project Schedule
Math and Science (New Construction) Overview: The construction consists of a new three story math/science complex including a 70,000 sf laboratory core, with primarily dry labs on the first floor, wet Biology labs on the second floor, and chemistry labs on the third floor. There is 20,000 sf of office space and 20,000 sf of classrooms on each floor dedicated to each discipline, primarily in separate zones. The labs wrap around a central service core consisting of tech offices, lab preparation rooms, and lab storage rooms. Students will enter the labs from the opposite side of the central service core providing safe separation of students and chemicals. Student break-out spaces, computer labs, and a resource center for studying and tutorial sessions will be provided. During the programming and planning effort the building was sited north of the existing Shima Center. This location was chosen due to its proximity to public and student parking for easy access to the proposed future Planetarium and the Math/Science building, as well as a separate service drive for easy access to the labs. The new building replaces an outdated 92,000 sf science building currently in use. The exterior building’s form, materials and colors reflect a modern interpretation of the “Village” character of the existing campus buildings. This is a State funded project with a 50% match with local funds.
Math and Science (New Construction) • Where: Project Location
Math and Science (New Construction) Original Project Information: Area: 110,000 g.s.f. Contract Award: January 2010 Complete Construction: March 2013 Architect: tBP Contractor: Taisei
Math and Science (New Construction) Current Project Status: Budget: On Budget. Project is 50% state funded. Schedule: Revised Completion Date for Phase I is March 2013 Change Orders: 25 General Problems: N/A Safety Problems: N/A
Math and Science (New Construction) Project Budget and Expenditures
Math and Science (New Construction) • When: Project Schedule Math and Science
Manteca Barn, Shade, and Fence Overview: The project entails the new construction of a pre-engineered metal building to serve as a barn, laboratory, & teaching facility. The new barn will have a canopy and new perimeter fencing enclosing the rear of the structure to facilitate the herding of livestock.
Manteca Barn, Shade, and Fence • Where: Project Location
Manteca Barn, Shade, and Fence Original Project Information: Area: 3600 g.s.f. Contract Award: August 2013 Complete Construction: March 2014 Architect: ANOVA Contractor: To be determined
Manteca Barn, Shade, and Fence Current Project Status: Budget: On Budget Schedule: Project has been put on hold Change Orders: N/A General Problems: None Safety Problems: None
Manteca Barn, Shade, and Fence Project Budget and Expenditures
Manteca Barn, Shade, and Fence • When: Project Schedule
ShimaHeavy Equipment / Diesel Expansion • Overview: • This project provides for a modest expansion of the Shima Center in order to expand the heavy diesel engine, hydraulics and repair program, and to allow the auto program to expand in Holt. The expansion includes additional shop space, an exterior open air laboratory and a new diesel laboratory shop area.
ShimaHeavy Equipment / Diesel Expansion • Where: Project Location
ShimaHeavy Equipment / Diesel Expansion Original Project Information: Area: 12,000 g.s.f. Contract Award: November 2012 Complete Construction: January 2014 Architect: Lionakis Contractor: Seward L. Scheder
ShimaHeavy Equipment / Diesel Expansion Current Project Status: Budget: On Budget Schedule: On Schedule Change Orders: N/A General Problems: None Safety Problems: None
ShimaHeavy Equipment / Diesel Expansion Budget and Expenditure Report:
ShimaHeavy Equipment / Diesel Expansion • When: Project Schedule
Stockton Campus Restroom Renovations • Overview: • The scope will consist of renovating several restrooms on campus to meet current building codes and update fixtures to the District’s current standards. The restrooms scheduled for the renovation are contained within the following buildings: Administration, Atherton, Budd, Danner, Forum, Locke, and Shima.
Stockton Campus Restroom Renovations • Where: Project Location
Stockton Campus Restroom Renovations Original Project Information: Area: N/A g.s.f. Contract Award: April 2013 Complete Construction: September 2013 Architect: Lionakis Contractor: To be determined
Stockton Campus Restroom Renovations Current Project Status: Budget: On Budget Schedule: Project Bidding Change Orders: N/A General Problems: None Safety Problems: None
Stockton Campus Restroom Renovations Budget and Expenditure Report:
Stockton Campus Restroom Renovations • When: Project Schedule
Question and Answer March 12, 2013