An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Facilities Report Zionsville Community Schools

  2. Facilities & Grounds Overviewby the Numbers • Acres—558 • Farm Lease--200 • Buildings—11 • School Buildings—8 • 3 Secondary, 5 Elementary • 5 have been constructed since 2001 • Each of the remaining 3 have had significant refurbishing since no later than1998 • Support Buildings—3 • SF Under Roof--1,654,012

  3. Facilities & Grounds Overviewby the Numbers • Maintenance and Grounds Employees—11 • Custodians—43 • Ratio of SF to Custodian • Industry Average—26,000-28,000 • ZCS—40,347 Peer District • 20 maintenance • 60 custodians

  4. ZCS Facilities

  5. Essential Questions • How do we pay for the upkeep of our facilities? • What are our needs? • What are our plans to pay for these needs? • Are we adequately accommodating student enrollment?

  6. Prioritizing Needs • Criteria • Safety and Security • Regulatory Compliance • Structural Integrity • Stratified Approach to Timing • Preventative Maintenance and Safety • Immediacy • Long term

  7. Stratified Approach to Needs • Preventative Maintenance & Safety Items • Maintenance Agreements (Boilers, Chillers, Etc.) • Bleacher and Playground Inspections & Maintenance • Parking Lots • High Voltage Inspections & Maintenance • Emergency Shutdown Systems • Gym Floors • Painting • Mandated Upgrade of Radio Communication System • Immediate Needs • Roof (ZCHS) • Carpet • Technology--Backup for MDF (ZCHS) • Technology– Cooling System for MDF • Foundation Repairs at Eagle • Athletic Facilities Repairs • Fire Alarm Upgrades • Repair/Maintain Sewage Lift Station (BME)

  8. Stratified Approach to Needs Stratified Approach to Needs • Long Term Needs • Upgrades to Water Heaters • Installation of UV Units for HVAC • Software and Hardware Upgrades for HVAC Controls • Boiler Upgrade/Replacement (PVE) • Upgrade Fire Suppression System (PVE) • Foundation Remediation (EE) • Security Access System (Trans) • Equipment and Vehicle Upgrades or Purchases (Maintenance)

  9. Focus on ZCHS Roof • Approach—Avoid Incurring Debt Through Phased Process • 3 Priority Based Phases • Phase 1—2012-13 • 40% of Project • Bid Process Fall 2012 • Implementation Spring/Summer 2013 • Phases 2—2013-14 • 40% • Phase 3—2014-15 • 20%

  10. Building Capacity—Potential Concerns

  11. Capacity Pinch Points: ZCHS and Stonegate Elementary ZCHS at1,839 as of 8/1/2012 This EXCEEDS 2013 projection

  12. Building Capacity Pinch Points • Stonegate Elementary School • 663 Students—110% • Space is maximized • Gained 34 students during last school year • Present Class Size --metric/+3 across grades • Timeline for action • December 2012/January 2013—Acquire/Review Demographic Study • February-March 2013—Gather Options • April—Recommend Action to School Board

  13. Building Capacity Pinch Points • Zionsville Community High School • 1,839 Students—91% • Possible Approaches—Leadership Imperative: No new debt! • Possible alternatives (perhaps in combination) • Additional space at ESC (ESC moves to another location) • Additional space at Pleasant View Elementary • Creative scheduling/calendaring • Hybrid courses/online coursework • Three-year graduate initiative (Mitch Daniels Scholarship) • Timeline— • Present—Internal discussions ongoing • December 2012-January 2013—Review Demographic Study • Fall 2013—Formalize Discussions • Target to Initiate Solutions—2014

  14. Essential Questions • How do we pay for the upkeep of our facilities? • From the Building Capital Maintenance slice of the CPF • What are our needs? • Needs are prioritized based upon established criteria. Debt avoidance is accomplished through this stratified approach and the phasing of large ticket items such as the HS roof. • What are our plans to pay for these needs? • Take advantage of the mitigation of circuit breaker loss made possible by the debt restructuring in 2013-2015. • Are we adequately accommodating student enrollment? • Yes, but the over capacity at SGE and the nearing capacity at ZCHS must be addressed, thus this foreshadowing of planning activities

  15. Facilities Report Zionsville Community Schools