CREZ Implementation Study Update

CREZ Implementation Study Update. Warren Lasher Manager, System Assessment. Purpose. In the Final Order in Docket 35665, ERCOT was asked to file sequencing recommendations by May 29, 2009 for non-default and non-priority lines

yaphet
Download Presentation

CREZ Implementation Study Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CREZ Implementation Study Update Warren Lasher Manager, System Assessment Regional Planning Group

  2. Purpose In the Final Order in Docket 35665, ERCOT was asked to file sequencing recommendations by May 29, 2009 for non-default and non-priority lines What is being sequenced at this point is the order of the CCN filings, but this will be based on the general order in which the lines should be completed : Default : Priority Regional Planning Group

  3. Overall Strategy for Sequencing • Schedule projects so that construction is completed by end of 2013 consistent with PUCT Order • CCNs for longest lines have to be near the top of the schedule • Meet PUCT Staff request for CCN timing and frequency • File CCN Applications for projects that connect to load centers first • These projects are required in order to increase transfer capacity Regional Planning Group

  4. Overall Strategy for Sequencing (II) • Try to establish some level of connectivity to as many of the CREZ collection points as quickly as possible • Complete the connection to the Odessa area quickly Regional Planning Group

  5. Current Status of Sequencing Recommendations • ERCOT developed a straw-man proposal based on the Joint Parties’ filing in docket 35665 • Joint Parties’ plan was modified to reflect new start date and the goals stated above • Comments were received from the TSPs and by PUCT staff • Construction schedules were adjusted by TSPs that were awarded projects but who were not included in the Joint Parties • ERCOT has submitted its third iteration to the TSPs and PUCT staff for review and comment Regional Planning Group

  6. Remaining Steps Finalize sequencing recommendations based on additional comments from TSPs and RPG Submit report to PUCT by May 29, 2009 Regional Planning Group

  7. Latest Draft Proposal The following slides represent the latest pass in an iterative process that has not yet been completed. Dates presented are based on estimated completion dates given the current iteration of the CCN filing sequence and are still being revised in discussions with the TSPs and PUCT staff. These dates are only general timeframes at this point Some projects may be combined in the CCN process Maps show quarterly progress - all lines brought into service in specified time period Regional Planning Group

  8. Regional Planning Group

  9. Regional Planning Group

  10. Regional Planning Group

  11. Regional Planning Group

  12. Regional Planning Group

  13. Questions? Regional Planning Group