MOM report

MOM report. Period 29/9/2011 – 5/10/2011 Giorgio CECCHET. MOM report. On Sept. 29 th , we had another run to test the target. It’s behaviour was excellent and look in eLog 1823 to see various comments from the shifters.

yestin
Download Presentation

MOM report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MOM report Period 29/9/2011 – 5/10/2011 Giorgio CECCHET

  2. MOM report • On Sept. 29th, we had another run to test the target. • It’s behaviour was excellent and look in eLog 1823 to see various comments from the shifters. • No major problems with the magnets of the beamline. Few small problems solved on the spot and we run with a full set of magnets (except the DS).

  3. MOM report • HV to the TOF’s was put on remotely by Pierrick. I suggest to Pierrick to add the possibility to load all HV’s at once using a file containing the standard set of voltages for TOF’f and KL. Loading the voltages one by one is too cumbersome and time consuming. • DAQ: some problems connected with some hardware in one crate (missing voltage at the power supply) and other (see again eLog 1823-1827).

  4. MOM report • Hall conditioning: severe water leakage from conditioning unit 1, just above the HV crates for TOF’s etc. Switched off. Need repair before Dec runs. • Comments: I suggest to power on the magnets of the beamline at least once a week and let the current flow (e.g.100A) for some time (e.g. half an hour). This until we start running again.

  5. MOM report • Yesterday we had the “MICE Hydrogen System Pre-Operation Safety Review”. See presentations in the web page.