Herriman City Municipal Water

Herriman City Municipal Water. PowerPoint Presentation March 10, 2011. System Maintenance. Service of Booster Pumps & Wells Fire Hydrant Flushing Valve Exercising Tank Cleaning. Service Of Booster Pumps & Wells. Shut Down Power/Lockout- Tagout Disassemble Pump Clean All Parts

yovela
Download Presentation

Herriman City Municipal Water

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Herriman City Municipal Water PowerPoint Presentation March 10, 2011

  2. System Maintenance • Service of Booster Pumps & Wells • Fire Hydrant Flushing • Valve Exercising • Tank Cleaning

  3. Service Of Booster Pumps & Wells Shut Down Power/Lockout-Tagout Disassemble Pump Clean All Parts Replace All Bearings, Packings & Seals Repair Or Replace Other Parts As Needed Reassemble Pump Realign Pump Lubricate With Ultra Sound Equipment Test & Bring Back On Line

  4. Pump Shaft Alignment Ultra Sound Equipment

  5. Fire Hydrant Flushing & Valve Exercising Annually We Flush & Inspect All Fire Hydrants & Dead Ends With The Assistance Of Unified Fire Fully Close & Reopen Each Valve In Our Water System

  6. Tank Cleaning Clean, Inspect & Video Every 3-5 Years Why? This Provides Us With Visual Conditions Of The Inside Of Our Tanks This Allows Us To Clean The Tanks Without Taking Them Off-Line. All Our Water Tanks Were Cleaned In November 2010

  7. Projects • Well 1 Booster Station • Chlorine & Fluoride Analyzer • 5600 W Culinary & Secondary Water Lines • Early Stages of Implementation Of Secondary Water System • Mountain View Corridor Betterments

  8. Well 1 BoosterPumpStationCompleted

  9. Chlorine & Fluoride Analyzer Installed At Well 1, HP Tanks & The RoseCrest Booster Pump Station Provides Trending Of Fluoride & Chlorine Levels Connected To The SCADA System Which Allows Off Site Tracking & Control Of Chemical Levels. Analyzers Provide Additional Safety To The Water System & Our Residents

  10. Silver Spur Construction Won Bid Project Will Begin March 16, 2011 This Project Has A Completion Time Of 90 Days

  11. Secondary Water System Secondary Water Rate Study-Bowen Collins Project Will Go Out To Bid Early Summer Purple Shaded Area Will Be First Area To Receive Secondary Water

  12. Mountain View Corridor March 2011 The Betterments Are Approximately 50% Completed Trench is 32’ There Is A 32” Culinary & 10” Secondary HDPE Pipe

  13. ? ? ? ? ?Questions