An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Planning for slab-on-ground placement Chapter 1

  2. Chapter Topics • Introduction • Specification requirements • Determining the size of concrete placements • Ordering concrete • Concrete delivery • Equipment • Size of placing and finishing crews • Preconstruction meeting

  3. Specification Requirements • ACI flatwork finishers • Material properties • Concrete strength and durability • Vapor retarders or barriers • Reinforcement • Slab flatness and levelness • Joint spacing and depth • Curing and protection

  4. Concrete Delivery • Concrete is perishable—be prepared • Site access—flagger needed—cone area • Space for two trucks to discharge • ASTM C 94 Specification for Ready-Mixed Concrete • Discharged within 1 ½ hrs or 300 revolutions • Plan for ready mix trucks • Spacing of trucks, 15 minutes? • Discharge of trucks, 5 to 15 minutes • Washout of trucks

  5. Have Equipment Ready • And spare equipment • Emergency bulkheads • Equipment Producitivity • Hand finishing crew: 1000 to 2000 sf • Walk-behind: 1000 to 3000 sf • Ride-on trowel: 3000 to 6000 sf • Laser-guided, wheel-mounted screed: 30,000 to 50,000 sf

  6. Size of Placing and Finishing Crews • Labor cost for placement • Workers sick or injured • Concrete sets faster • Weather changes; hot or rain • Equipment breakdowns • Early sawing to minimize cracking • Overlap placing and finishing crews

  7. Placing Crew • Finishing foreman • Discharging concrete • Spreading concrete • Screed operators • Finishers • General assistance

  8. Finishing Crew • Concrete and Weather • Working edges • Walk-behind to float fast-setting loads • Riding trowels • General assistance

  9. Checklist for Placing and Finishing • Volume of concrete • Concrete delivery rate • Haul time • Truck spacing • Placing equipment • Spare equipment • Crews

  10. End of Chapter 1