Progress Report Implementing the Interregional Transportation Strategic Plan May 22, 2003 in Sacramento Brian Smith, Deputy Director, Planning and Modal Programs California Department of Transportation. Interregional Transportation Strategic Plan.
E N D
Progress ReportImplementing the Interregional Transportation Strategic PlanMay 22, 2003 in SacramentoBrian Smith, Deputy Director, Planning and Modal ProgramsCalifornia Department of Transportation
Interregional Transportation Strategic Plan • Guiding Interregional Improvement Program Investment • Improving Interregional Movement of People and Goods • Vision, Strategies, Performance Measures, Principles, and Objectives
Interregional Transportation Strategic Plan Six Objectives • Complete a Trunk System – Focus Routes • Connect Urbanized Areas to Freeway-Expressway System • Ensure Dependable Travel into Major Gateways and Connectivity to Major Intermodal Transfer Facilities • Connect Urbanizing Centers to Trunk • Link Rural and Smaller Urban Centers to Trunk • Intercity Passenger Rail Program
Interregional Transportation Strategic Plan Objective 1 – Complete a Trunk System • 10 Routes and Route Portions for Focused IIP Investments • Meet Current and Future Population Needs • Major Underdeveloped North – South and East – West Routes • Focus Routes plus Interstate System Ensures Strong Transportation System
Interregional Transportation Strategic Plan Focus Routes and Goods Movement Benefits Major North – South Routes for Goods Distribution and Transfer • STAA (Big Trucks) and Terminal Access Routes • 5 Axle Truck VMT - Interstates 57% - Focus Routes 26% • Principal East – West Access Over Coast Range and Connections from I-15/40 into Central Valley Peak Agricultural Season, Timber, Mining
Interregional Transportation Strategic Plan Objective 2 - Connect All Urbanized Areas to F&E 55 Urbanized areas in CA Those Designated Urbanized in Last 30 Years • 13 on Interstates • 24 on Focus Routes • 9 on Focus Routes and Interstates • 9 Within Proximity of Focus and Interstates
Interregional Transportation Strategic Plan Objective 3 –Dependable Movement Into Major Gateways & Connectivity to Key Intermodal Transfer Facilities • Bay Area, Southern CA, Mexico, Grapevine and Central Valley • International Airports, Air Cargo Terminals, Seaports, Freight Distribution Facilities • Goods Movement - STAA Routes and Truck Terminal Access
Interregional Transportation Strategic Plan Objective 4 – Connect Urbanizing and High Growth Centers to Trunk Anticipate New Centers to Follow Historical Trends • 2000 Census added 10 New Urbanized Areas - Six on Focus Routes - Three on Interstates - One in Proximity to Focus • 2040 Population Added to SR 99 Co’s – 5.2 M and US 101 – 3.2 M • Importance of Focus Routes Development - 13 Urbanized Areas on SR 99 - 13 on US 101 from Ventura Co. North
Interregional Transportation Strategic Plan Objective 5 – Link Rural and Smaller Centers to Trunk • California 3rd Largest State • 156 Thousand Square Miles • 86% State Population in Urbanized Areas on 4.2% of Land • Many Rural and Small Towns • Susanville, Williams, San Juan Bautista, Chowchilla, Bishop and Oasis
Interregional Transportation Strategic Plan Objective 6 – Intercity Passenger Rail • Complies with Fed and State Law • Improves Service Reliability • Decreases Running Times • Reduces Per-Passenger Operating Subsidy
Interregional Transportation Strategic Plan Progress Towards Meeting Objectives • Focus Routes Projects - 210 Projects Needed to Complete Routes - 99 Projects Full or Partially Programmed Dollars Total to Complete - Estimate $7.5 Billion - Programmed $2.6 Billion - $1.3 IIP (incl. Grandfathered) - $1.3 RIP
Interregional Transportation Strategic Plan Overall Progress Towards Meeting Objectives • Comprehensive Interregional Improvements • Interstates, IRRS Routes, Other Routes, Intercity Passenger Rail, Grade Separations, Multi-modal IIP $’s Programmed ’98 – ’02 STIPs
Interregional Transportation Strategic Plan Strategy for Continued Improvement of Interregional Mobility • Stay Focused on Completing Trunk System • Participate with Regions in Optimization of Interstates for Selected Projects • Selected non-Trunk and Interstate IRRS Improvements • Rural Partnerships • RIP $’s On System