1 / 15

RSRDC

RSRDC. UNIT- II, AJMER. ORGANISATION CHART OF RSRDC UNIT-II, AJMER. P.K.Arora. Vacant (Addl. Charge to Sh. Sunil jain. ARE. Sh. Lokesh Gupte Sh. Lalit Sharma. 3. Sh. Ashish Sharma 4. Sh. Harsh Rai. Financial Work Load in Unit. Rs. In Lacs.

Anita
Download Presentation

RSRDC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RSRDC UNIT- II, AJMER

  2. ORGANISATION CHART OF RSRDC UNIT-II, AJMER P.K.Arora Vacant (Addl. Charge to Sh. Sunil jain ARE • Sh. Lokesh Gupte • Sh. Lalit Sharma • 3. Sh. Ashish Sharma • 4. Sh. Harsh Rai

  3. Financial Work Load in Unit Rs. In Lacs

  4. Important Works Completed during last 5 years Regional Pollution Control Board office, Bhilwara Completion Cost – Rs. 23.97 lacs

  5. Construction of ROB at Kishangarh, Ajmer Total Cost : Rs. 10.00 Crores Location : Kishangarh, Ajmer Date of Start : 18.03.2007 Stipulated Date of Completion : 17.01.2008 Expenditure till Date : Rs. 843.96 Lacs Likely Completion date : 30.6.2010 (Depends on Railway work) Bottlenecks if any : Two nos span and finishing dependant on railway work Status of railway work : Sub structure work completed. Idle since last six months due to finalisation of drawing & design of super structure.

  6. Construction of ROB at Saradhna, Ajmer Total Cost : Rs. 10.00 Crores Location : Beawar road, Ajmer Date of Start : 17.07.2007 Stipulated Date of Completion : 16.06.2008 Expenditure till Date : Rs. 783.56 Lacs Likely Completion date : 31.12.2010 (Depends on Railway work) Bottlenecks if any : Gap slab connecting rly. portion and finishing dependant on railway work Status of railway work : Lay out & shifting of cable work in progress.

  7. Construction of ROB at Bhilwara(UIT Work) Total Cost : Rs. 20.86 Crores Location : Bhilwara Date of Start : 18.03.2007 Stipulated Date of Completion : 17.11.2007 Expenditure till Date : Rs. 1327.31 lacs + Rs385.00 lacs (Rly.) Likely Completion date : 31.05.2010 (Depends on Railway work) Bottlenecks if any : Two nos span and finishing dependant on railway work Status of railway work : Sub structure work completed. Super structure work in progress.

  8. Construction of ROB at Mandal (Bhilwara) Total Cost : Rs. 10.00 Crores Location : Mandal, Bhilwara Date of Start : 19.07.2007 Stipulated Date of Completion : 18.06.2008 Expenditure till Date : Rs. 870.46 Lacs Likely Completion date : 30.06.2010 (Depends on Railway work) Bottlenecks if any : Two nos span and finishing dependant on railway work Status of railway work : Sub structure work in progress.

  9. Construction of ROB at Makrana Distt. - Nagour) Total Cost : Rs. 10.00 Crores Location : Makrana, (Distt.-Nagour) Date of Start : 23.08.2008 Stipulated Date of Completion : 22.07.2009 Expenditure till Date : Rs. 390.67 lacs. Likely Completion date : 30.09.2010 (Depends on Railway work) Bottlenecks if any : Shifting of electric lines & encroachments. Status of railway work : Work order placed. Work yet not started.

  10. Construction of ROB at Nagour Total Cost : Rs. 13.00 Crores Location : Nagour Date of Start : 21.08.2008 Stipulated Date of Completion : 20.07.2009 Expenditure till Date : Rs. 405.45 lacs. Likely Completion date : 30.09.2010 (Depends on Railway work) Bottlenecks if any : - Status of railway work : Work order issued. Work yet not started.

  11. Construction of ROB at Dholpur Total Cost : Rs. 10.00 Crores Location : Dholpur Date of Start : 17.11.2007 Stipulated Date of Completion : 16.10.2008 Expenditure till Date : Rs. 609.36 lacs. Likely Completion date : 30.09.2010 (Depends on Railway work) Bottlenecks if any : - Status of railway work : Work order issued. Work yet not started.

  12. Construction of ROB at Mania-Marena Road Total Cost : Rs. 10.00 Crores Location : Mania, Dholpur Date of Start : - Stipulated Date of Completion : - Expenditure till Date : Rs. 0.03 lacs. Likely Completion date : Bottlenecks if any : The present LC No. 472 is a part of Bye pass for ROB at LC No. 463. Hence traffic is to be bye passed at LC No. 473 which requires interlocking. Railway has agreed for interlocking & up gradation. Which shall be completed by Feb-2010. Revised A&F required amounting to Rs. 16.15 Crore Estimate Submitted to CE PWD through ACE Zone Bharatpur Status of railway work : Revised GAD pending at Railway part for approval, likely to be received in Dec. 2009’

  13. Proposed New Works

  14. THANKS

More Related