Project Status Project Phasing Questions. Project released for Bid February 7, 2011 Notice of Bid sent to 80+ Contractors on February 2, 2011 C&S occupied the field office on January 18, 2011 Architectural Approval from SED on December 17, 2010. As of Today. Moving Forward .
E N D
Project Status Project Phasing Questions
Project released for Bid February 7, 2011 • Notice of Bid sent to 80+ Contractors on February 2, 2011 • C&S occupied the field office on January 18, 2011 • Architectural Approval from SED on December 17, 2010 As of Today
Moving Forward • Contractor walk through scheduled for February 22, 2011 • Project Bids accepted March 3, 2011 • Contractor recommendations to the BOE on March 8, 2011 • Contractor mobilization beginning in early April, 2011
Phasing : • Scheduling Goals: • Minimize disruption to students / staff during the school year • Upgrade HVAC systems by September 2011 • Main Campus Overall Staging Area • Large Permanent Staging Area in gravel lot below the District Office • Summer Lay Down Areas at both the High School and Wheeler Elementary School
HIGH SCHOOL : • TWO PHASES SUMMER 2011 & SUMMER 2012 • SUMMER 2011 • HVAC UPGRADES • MAIN OFFICE/GUIDANCE/HEALTH SUITE • FIRST FLOOR CLASSROOM RENOVATIONS • SINGLE SCEINCE CLASSROOM RENOVATION • ROOFING
HIGH SCHOOL : • SUMMER 2012 • TWO SCIENCE CLASSROOMS • SECOND FLOOR CLASSROOM RENOVATIONS • MEDIA CENTER RENOVATIONS • SITEWORK
TECHNOLOGY BUILDING: • UPGRADES COMPLETED BY SEPTEMBER 2011
WHEELER ELEMENTARY: • SUMMER 2011 • PROJECT COMPLETED • HVAC UPGRADES • ROOFING • CLASSROOM RENOVATIONS
ROCKWELL ELEMENTARY: • TWO PHASES – SUMMER 2011 & SUMMER 2012 • SUMMER LAY DOWN AREA • SUMMER 2011 • HVAC UPGRADES COMPLETED • ROOFING • ADMINSTRATIVE AREA • SECOND FLOOR WEST WING CLASSROOMS
ROCKWELL ELEMENTARY: • SUMMER 2012 • FIRST FLOOR CLASSROOMS • SECOND FLOOR EAST CLASSROOMS • SITEWORK