Project Status Project Phasing Questions

Project Status Project Phasing Questions. Project released for Bid February 7, 2011 Notice of Bid sent to 80+ Contractors on February 2, 2011 C&S occupied the field office on January 18, 2011 Architectural Approval from SED on December 17, 2010. As of Today. Moving Forward .

afra
Download Presentation

Project Status Project Phasing Questions

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Status Project Phasing Questions

  2. Project released for Bid February 7, 2011 • Notice of Bid sent to 80+ Contractors on February 2, 2011 • C&S occupied the field office on January 18, 2011 • Architectural Approval from SED on December 17, 2010 As of Today

  3. Moving Forward • Contractor walk through scheduled for February 22, 2011 • Project Bids accepted March 3, 2011 • Contractor recommendations to the BOE on March 8, 2011 • Contractor mobilization beginning in early April, 2011

  4. Phasing : • Scheduling Goals: • Minimize disruption to students / staff during the school year • Upgrade HVAC systems by September 2011 • Main Campus Overall Staging Area • Large Permanent Staging Area in gravel lot below the District Office • Summer Lay Down Areas at both the High School and Wheeler Elementary School

  5. HIGH SCHOOL : • TWO PHASES SUMMER 2011 & SUMMER 2012 • SUMMER 2011 • HVAC UPGRADES • MAIN OFFICE/GUIDANCE/HEALTH SUITE • FIRST FLOOR CLASSROOM RENOVATIONS • SINGLE SCEINCE CLASSROOM RENOVATION • ROOFING

  6. HIGH SCHOOL : • SUMMER 2012 • TWO SCIENCE CLASSROOMS • SECOND FLOOR CLASSROOM RENOVATIONS • MEDIA CENTER RENOVATIONS • SITEWORK

  7. TECHNOLOGY BUILDING: • UPGRADES COMPLETED BY SEPTEMBER 2011

  8. WHEELER ELEMENTARY: • SUMMER 2011 • PROJECT COMPLETED • HVAC UPGRADES • ROOFING • CLASSROOM RENOVATIONS

  9. ROCKWELL ELEMENTARY: • TWO PHASES – SUMMER 2011 & SUMMER 2012 • SUMMER LAY DOWN AREA • SUMMER 2011 • HVAC UPGRADES COMPLETED • ROOFING • ADMINSTRATIVE AREA • SECOND FLOOR WEST WING CLASSROOMS

  10. ROCKWELL ELEMENTARY: • SUMMER 2012 • FIRST FLOOR CLASSROOMS • SECOND FLOOR EAST CLASSROOMS • SITEWORK

  11. Questions