310 likes | 334 Views
Water Right Transfers OAR Chapter 690, Division 380. Transfer = Change. Place of use (including to instream) Character of use (Type) Move a point of Point of Diversion (POD) / Point of Appropriation (POA) Add POD’s and/or POA’s. Some things don’t Change. Priority Dates
E N D
Transfer=Change • Place of use (including to instream) • Character of use (Type) • Move a point of Point of Diversion (POD) / Point of Appropriation (POA) • Add POD’s and/or POA’s
Some things don’t Change • Priority Dates • The Amount of Water allowed to be beneficially used
Types of Transfers • Permanent (many varieties) • Temporary up to 5 years (25 yrs in Deschutes Basin) • District Permanent • District Temporary • Substitution • Water exchange • Permit Amendment • Groundwater Registration Modification • Historic Point of Diversion • Instream
Who can do a Transfer? • Irrigation Districts • Water right holders • Any individual or entity with permission from the water right holder
What’s Needed First? • A “water right subject to transfer” • Perfected or decreed right with a non-cancelled Certificate • Approved previous transfer for which a Claim of Beneficial Use (COBU) has been received (however, the new transfer cannot be approved until the previous transfer’s COBU is approved, as evidenced by a confirming certificate) • Permit (only if a supplemental is moving with its primary certificated right, or if request is a substitution or permit amendment)
Valid Water Right or Permit • The right must be valid and not subject to forfeiture. • Used within the last 5 years if it’s a certificated right, or • It qualifies for an exception under ORS 540.610 • Not past the Completion date (C-date) if a permit amendment
Must haves “attachments” • Affidavit of Use • Documentary evidence of use (to back up what’s asserted in the affidavit) • Map or maps showing the “authorized, from or off” status, and the “proposed, to, or on” changes, A CWRE map required unless it is a temporary, historic POD, permit amendment or a district transfer) • Land use form (unless ALL 4 exceptions are satisfied) • Well log for each existing well and proposed construction info for each proposed well
Reasons an application may be returned Include • Missing fees • Not signed (need all landowners signatures) • Incomplete application (missing attachments) • Map doesn’t meet standards • Right not subject to transfer (the permit expired, cancelled certificate, Claim of Beneficial Use (COBU) has not been approved, etc.
What is Injury? • “Injury” or “Injury to an existing water right” means a proposed transfer would result in another, existing water right not receiving previously available water to which it is legally entitled.
Would there be injury? • “Injury to an existing water right means a proposed transfer would result in another, existing water right not receiving previously available water to which it is legally entitled.” OAR 690-380-0100(3) • Are return flows visibly coming from the place of use? • Are return flows from the use available to downstream rights calling on the same source? • If the full quantity of water were used, would there be return flows? • If there were return flows, where would they go--back to the source, another stream, upstream/downstream of other PODs?
More about Injury • Diversion of water at the full rate and/or duty for the currently authorized use would be wasteful • If so, may need to limit transfer amount • May be less of an issue if character of use not changed • Upstream movement of the POD would reduce flow in a reach where an instream water right will not be met • Intervening PODs between authorized and proposed PODs • Change in POD would be upstream within/into instream water right reach
Continued… • Streamflows insufficient to meet all rights • how frequently? • Less water available to the transferred right at the new POD due to channel losses (this could lead to an increase in calls against upstream junior users) • portion of flow lost? • Significant inflow between authorized and proposed POD
Consent to Injury • OAR 690-380-5030, 5040, 5050 • Water right holder may consent to injurious POD change • Out-of-stream users must sign affidavit consenting • WRD may consent to injury of instream rights • typically involves upstream movement of POD • only on recommendation of ODFW/DEQ/Parks • change must produce net benefits for the resource
What is Enlargement? • “Enlargement” means an expansion of a water right and includes, but is not limited to: • (a) Using a greater rate or duty of water per acre than currently allowed under a right; • (b) Increasing the acreage irrigated under a right; • (c) Failing to keep the original place of use from receiving water from the same source; or • (d) Diverting more water at the new point of diversion or appropriation than is legally available to that right at the original point of diversion or appropriation.
Wouldtherebeenlargement?? • If the Original place of use continues to receive water from the same source • If there is More water available at new Point of Diversion (POD) than legally available at original • If More water is available at new Point of Appropriation (POA) than legally available at original • Any Increase in acreage irrigated
Is the Right Valid? • Available information indicates the right has been used during the past five years • If we go to cancellation, we will need to develop the supporting information • A presumption of forfeiture likely would be overcome • One of the 20+ (and counting) exceptions under ORS 540.610 is present
Ready, Willing, Able? • System capacity to divert full quantity allowed under transferred portion of right • If not now, then within last five years? • Transmission and application capability to use water on all lands involved in the transfer • If not now, then within last five years?
Changes in POD/POA • Is this an additional POD/POA or a change in POD/POA (for the portion of the right involved in the transfer)? • Is the movement upstream or downstream? • Is the new POA/POD more than ¼mile from the authorized point? • Are there intervening points of diversion? • Are there significant areas of inflow or losing reaches between proposed & authorized points?
“From” Lands • Ownership • Application and map to existing right should be consistent with the water right of record • If you intend to move the Place of Use- check plat card for other rights appurtenant to the “from” lands
Identifying the “To” Lands • Checking for other rights –underlying rights may need to be diminished or cancelled. • The Department will work with applicant to resolve conflicts • Diminishment of right to supplemental • Voluntary cancellation • Amend transfer to change “to” lands to avoid overlap
Sequence of communication • Deficiency letter sent to applicant if application needs major revisions • Draft Preliminary Determination (DPD) & Cover Letter to applicant, with copy to Watermaster, Agent, and CWRE • can be used to identify deficiencies • allow modification of application within 30 days • request is made now for Ownership Documentation • establish path to issue final PD absent response
Process continued • Signed Preliminary Determination (PD) issued with copies to Watermaster, CWRE, commenters • Public notice on WRD website • Publication in newspaper for 2 consecutive weeks (applicant responsible for fees) • Protest period ends 30 days after WRD public notice or last date of newspaper publication, whichever is later
Protests, etc. • If protests filed, negotiate agreement or hold contested case hearing • Applicant may protest negative PD, or after Final Order is issued may petition for judicial review or reconsideration by the Director
Final Order • Issued consistent with PD if no protests • Approves or denies changes • Certificates are cancelled in most cases, & remaining right certificate issued for unaffected portion of the right • Applicant can begin to implement changes • Permanent changes must be completed by a specified date, or an extension is needed • Changes need to be proved up on, with submittal of a Claim of Beneficial Use
Proving Up • For Permanent OAR 690-380 transfers and Permit Amendments only: • Applicant completes changes and puts water to beneficial use by the Completion date (C-date), or applies for a “Transfer Extension of Time” • Applicant hires a CWRE to prepare a Claim of Beneficial Use (COBU) and Map • Then the Department reviews and approves COBU, and issues a new certificate for the changed right
Regular Transfer Application Accepted Noticed 30 day Comment Injury Review Temporary Draft Preliminary Determination Applicant Review of the Department’s Findings Final Order Public Notice-WRD & News paper Preliminary Determination