Marshall Marik Project Manager South Sacramento Streams Group Sacramento District May 17, 2012 SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE
Morrison Creek Construction Along Union Pacific Railroad • Construction started May 1st. • Coordinated with Union House Elementary School for placement of crossing guards. • Construction scheduled for completion in October 2012.
Post Authorization Change Report (PACR) • Preliminary FEMA floodplain information provided by the City of Sacramento contract indicates that a PACR will not be required. • Corps will complete verification of FEMA floodplain model by December 2012.