SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE

Marshall Marik Project Manager South Sacramento Streams Group Sacramento District May 19, 2011. SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE. Morrison Creek Construction Along Union Pacific Railroad.

aletta
Download Presentation

SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Marshall Marik Project Manager South Sacramento Streams Group Sacramento District May 19, 2011 SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE

  2. Morrison Creek Construction Along Union Pacific Railroad • Current schedule is to award end of this year, pending real estate rights from Union Pacific Railroad (UPRR). • Received tentative approval from UPRR for design at March 30th meeting. • Construction will not start until May 1, 2012 due to Endangered Species Act compliance.

  3. Post Authorization Change Report (PACR) • Sacramento City/County completed providing all existing hydrology on April 14th. Reviewing County General Plan with County staff to determine future hydrology. • Corps to complete hydrology review and start floodplain determinations next month. • Delay in receiving hydrology has caused PACR schedule to slip from completion in January 2014 to July 2014.

  4. Marshall Marik US Army Corps of Engineers 1325 J Street Sacramento, CA 95814-2922 (916) 557-7698