An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Griffin-Spalding County Airport LPA Group Project Update Presented to September 28, 2009

  2. Today’s Briefing • AIP -28 – Project Update • Crack Seal, Rejuvenate, and Marking of Existing Airfield • Repackage West Taxiway Rehabilitation Project • Design Itinerant Apron Rehabilitation • Environmental Study Update • Existing and New Airport

  3. AIP-28 – PROJECT UPDATE • Crack Seal, Rejuvenate and Marking • Entire Airfield Including Apron and Taxilanes • Scheduled to Start Construction Mid-October • Construction Duration Approx. 1 Month • Will Provide Extended Life to Existing Pavement • Will Give the Airport a Fresh Look

  4. AIP-28 – PROJECT UPDATE

  5. AIP-28 – PROJECT UPDATE

  6. AIP-28 – PROJECT UPDATE • Repackage and Rebid West Taxiway Improvements Project • Last Year’s Project – Pavement Reconstruction • Anticipate Construction Next Summer (depends on State Funding) • Rehabilitate Itinerant Apron Project • Overlay and Reconstruction of Terminal Area Apron • Anticipate Construction Next Summer (depends on State Funding)

  7. ENVIRONMENTAL UPDATE • Contracts Under GDOT Review • State Block Grant Requires GDOT to Review Contracts • Comments Expected Back This Week • Once Contract Finalized, Study Should Take Approximately 1 Year to Complete