50 likes | 144 Views
Marshall Marik Project Manager South Sacramento Streams Group Sacramento District July 21 , 2011. SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE. Morrison Creek Construction Along Union Pacific Railroad. Contract will be advertised for bids on July 22, 2011.
E N D
Marshall Marik Project Manager South Sacramento Streams Group Sacramento District July 21, 2011 SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE
Morrison Creek Construction Along Union Pacific Railroad • Contract will be advertised for bids on July 22, 2011. • SAFCA is working with UPRR to obtain real estate. • Construction will not start until May 1, 2012 due to Endangered Species Act compliance.
Post Authorization Change Report (PACR) • Floodplain determination work is on-going. • Reviewing County General Plan with County staff to determine future hydrology. • PACR is scheduled to complete in July 2014.
Marshall Marik US Army Corps of Engineers 1325 J Street Sacramento, CA 95814-2922 (916) 557-7698