South Sac Streams Group Burrowing Owl Mitigation Construction

South Sac Streams Group Burrowing Owl Mitigation Construction. By Lizette Crosbie Senior Natural Resource Specialist. Mitigation History. Impacts due to SSSG levee improvements Mitigation requirements: 2001-2006 impacts: 14  28 artificial burrows

oren
Download Presentation

South Sac Streams Group Burrowing Owl Mitigation Construction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. South Sac Streams Group Burrowing OwlMitigation Construction By Lizette Crosbie Senior Natural Resource Specialist

  2. Mitigation History • Impacts due to SSSG levee improvements • Mitigation requirements: • 2001-2006 impacts: 14  28 artificial burrows • 2007-2008 impacts: 41  82 artificial burrows • Installation of artificial burrow systems • March 2008  20 burrows • Fall 2008  ??? burrows

  3. Mitigation Location • Stone Lakes National Wildlife Refuge

  4. Artificial Burrow Construction March 2008

  5. Artificial Burrow Construction March 2008

  6. Artificial Burrow Construction March 2008

  7. Completed Artificial Burrow