EMODNet Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013 . EMODNet Lot 4 - Chemistry Overview, management and administrative issues Alessandra Giorgetti ( OGS ) with the contribution of Altenburger Alessandro, Brosich Alberto, Lipizer Marina, Partescano Elena, Vinci Matteo. Summary.
E N D
EMODNet Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013 EMODNet Lot 4 - Chemistry Overview, management and administrative issues Alessandra Giorgetti (OGS) with the contribution of Altenburger Alessandro, Brosich Alberto, Lipizer Marina, Partescano Elena, Vinci Matteo
Summary • EMODNet Chemistry 2 key elements and participants • EMODNet Chemistry 2 overview • EMODNet Chemistry 2 management • EMODNet Chemistry 2 coordination • Reporting to EU • Administrative issues EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
EMODNet Chemistry 2 - key elements • Proposal submitted 10th September 2012 • 32 partners + 14 subcontractors • 35 countries represented • Duration 3 years • Budget 4 M€ • Evaluation sent 4th April 2013 with documents integration • New documentary evidence sent 15th May 2013 • Waiting for EU Service Contract to be signed EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
EMODNet Chemistry 2 - partnership Based on SeaDataNet network of NODC’s with Technical partners to further develop and run SDN infrastructure Specific expertise to coordinate data analyses and validation, and the creation of data products 32 partners 14 subcontractors
EMODNet Chemistry 2 - overview Objective: • To build on what was achieved under preparatory actions; • To deliver a marine observation infrastructure that offers the most effective support to the marine and maritime economy whilst supporting environmental protection needs. Specific objectives are: • assemble existing data into interoperable formats • develop, test, operate and maintain a portal for public access • monitor and report on the effectiveness of the system in meeting the users needs and analyse what further steps are needed to improve the system • keep the portal operational and be prepared to transfer to the EC EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
The preparatory actions: 6 service contract are funded by DG-MARE for creating pilot components of the European Marine Observation and Data Network: hydrography, marine geology, chemistry, biology, habitats maps, physics. Started in 2009 3 years EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
EMODNet Chemistry 2 – 6 workpackages Workplan of the project Technical Annex Executed in 3 phases: construction (months 1-12) consolidation (months 13-24) convergence (months 25-36) EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Management: documents Service Contract - Consortium Agreement – Subcontracts EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Project management EC service contract with coordinator (OGS) Consortium Agreement with all partners including: • Technical Tender Form (Annex 3) • Table with budget breakdown • Banking references Subcontract with one-by-one all subcontractors including: • Technical Tender Form (Annex 3) • Banking references EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Management: structure Project coordinator (=OGS) Technical coordinator(=MARIS) Project office (=OGS) Workpackage leaders (=OGS, MARIS, ISPRA, ICES) Regional leaders for products (=AU-DCE, IFREMER, SMHI, HNODC-HCMR, NIMRD) Steering committee: (=OGS, MARIS, AU-DCE, IFREMER, SMHI, HNODC-HCMR, NIMRD, ISPRA, ICES). Project Coordination Group (all partners and subcontractors) EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Coordination: planned meetings The 7 thematic lots will meet with EU every 6 months to ensure convergence and collaboration between lots. The 7 thematic lots will meet with VLIZ and DG MARE to oversee development of an entry point portal. The 7 thematic lots will meet with WG-DIKE/MODEG to work collaboratively and support data access for MSFD assessment and monitoring. EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Coordination: planned meetings Any volunteer to host the first year plenary meeting? • Expected participants 70/80 people • Expected timing June/July 2014 EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Coordination: tools Mailing lists: • emodnet2-all@googlegroups.com • emodnet2-stcom@googlegroups.com • emodnet2-po@googlegroups.com Website: updating previous EMODNet Chemistry pilot Extranet for the project: • Restricted access (user: emduser, password: 91L07G207) • All project documents including contract EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Coordination: tools EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Reporting to EU: planning Deliverables: • Bimonthly concise progress reports through phases 1 to 3 (from M2 to M36) • First interim report after phase 1 (M12) • Second interim report after phase 2 (M24) • Draft final report 2 months before the end of phase 3 (M34) • Final report at the end of phase 3 (M36) • 15-page executive summary that can be read by a non-specialist EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Reporting to EU The bimonthly concise progress reports will be posted on the Maritime Forum, indicating meetings held, difficulties encountered, inventories of data made available (from M2) Interim and final reports have to be sent to EC for approval and payments, including summary of work done and what remains to be done, challenged faced, effort spent on data preparing and providing, developing standards(M12, M24, M34, M36) EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Administrative issues EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Administrative issues At the end of each period, the activity report and the relevant invoices have to be sent to EC by OGS After payment approval by EC, the relevant invoices or debit note or other official document have to be sent to OGS by all the partners and subcontractors EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013
Administrative issues: liquidated damages …the Commission may decide to impose liquidated damages per calendar day of delay according to the following formula: 0.3x(Volume/duration)=0.3x(3,999,999/1095)=1095,89 euro …such amount will be charged in proportion between all partners and subcontractors. It is much important to keep the scheduled date! EMODNET Lot 4 - Chemistry Kick-off meeting, 3-4 June 2013