1 / 16

Bond Construction Update Facilities Advisory Committee

Bond Construction Update Facilities Advisory Committee. Long Beach Community College District November 9, 2011. EDUCATE  ENGAGE  EMPOWER. Agenda. Completed Construction Projects LAC W Trailers Demo PCC Tech 1 (Sheet Metal) Current Construction Projects

fabian
Download Presentation

Bond Construction Update Facilities Advisory Committee

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bond Construction Update Facilities Advisory Committee Long Beach Community College District November 9, 2011 EDUCATE ENGAGE EMPOWER

  2. Agenda • Completed Construction Projects • LAC W Trailers Demo • PCC Tech 1 (Sheet Metal) • Current Construction Projects • LAC Building A – Student Services Retrofit • LAC Building I (Bookstore) • LAC Master Landscape • LAC Stadium Parking Lot Lights and Veterans Stadium Lights • PCC MDAB (Multi-Disciplinary Academic Building) • LAC PCC Building CC Retrofit • Upcoming Construction Projects • LAC Math Technology Building • PCC Building GG • LAC Building C Retrofit • Q & A

  3. Completed Construction Projects LAC W Trailers Demo - Measure E 2008 • Project addressed storm run off issues with bio swales • Site converted to a parking lot • Project completed Summer 2011

  4. Completed Construction Projects PCC Tech 1 (Sheet Metal) - Measure E 2008 • Construction started Summer 2011 • Equipment and utilities installed • Projected completed before start of Fall semester 2011

  5. Current Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 • New home for A&R, Counseling, Health Services, Cashier, Transfer Center • Project currently in structural upgrade • New contractor in place • End of construction anticipated Summer 2012

  6. Current Construction Projects LAC Building I - Measure E 2008 • Adds additional 4,000 square feet to existing building • Architecture to match LAC Mediterranean Theme • Work on framing and utilities underway • End of construction anticipated Fall 2011 • Move in planned for late January or early Feburary

  7. Current Construction Projects LAC Master Landscape - Measure E 2008 • Currently in Design Phase(Finalizing design) • Plans to be submitted to DSA November 2nd • Quad areas North and South of Bldg. A will bid Fall 2011 • Remaining areas designed at 25% • Scope includes new hardscape/landscape and pedestrian pathways

  8. Current Construction Projects Stadium Parking Lot Lights and Stadium Lighting Measure E 2008 • Stadium parking lot lights • Construction commenced 9/12 • All bases have been installed • Currently in the process of installing light poles/fixtures • Install energy efficient lights with controls capabilities • Stadium lighting retrofit • Awaiting final DSA approval

  9. Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2008 • MDAB building remodel project • Phase 1 of 2 currently under construction • Project currently in demolition and structural reinforcement • Phase 1 Project to be completed Summer 2012

  10. Upcoming Construction Projects PCC Building CC Retrofit - Measure E 2008 • Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices • Swing space located on PCC Campus (Bldg. GG) • Approved by DSA on 1/27/11 • Bid process complete. Awarded to Angeles • To be completed concurrently with MDAB project phase 1 • Anticipated end of construction Fall 2012

  11. Upcoming Construction Projects Will house Math and Culinary Arts instructional program as well as Reprographics Design Build delivery method Requesting Qualifications (RFQ) – was due 8/3 Shortlisted and interviewed 10 respondents (9/7-9/9) Selected 3 and are currently requesting for proposals Pre-RFP meeting with contractors to take place on 10/27 Anticipated start of construction 2013 LAC Math Technology Building – Measure E 2008

  12. Upcoming Construction Projects PCC Building GG - Measure E 2008 • Design Build delivery method • Request for Qualifications (RFQ) • Start in November and due mid December • Building to house Health Services, EOPS, DSPS, Financial Aid, Cashier, A&R, and Counseling • Estimated start of construction December 2013

  13. Upcoming Construction Projects LAC Building C Retrofit - Measure E 2008 • Hired Architect to do design work • Currently in schematic phase • Work includes modernization of structure, classrooms spaces, and office areas

  14. Liberal Arts Campus Site Plan l i b e r a l a r t s