Bond Construction Update Facilities Advisory Committee

Bond Construction Update Facilities Advisory Committee. Long Beach Community College District November 17, 2010. EDUCATE  ENGAGE  EMPOWER. Agenda. Current & Upcoming Construction Projects LAC Building A, Student Services Retrofit LAC Parking Structure LAC Building O Complex

hansel
Download Presentation

Bond Construction Update Facilities Advisory Committee

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bond Construction Update Facilities Advisory Committee Long Beach Community College District November 17, 2010 EDUCATE ENGAGE EMPOWER

  2. Agenda • Current & Upcoming Construction Projects • LAC Building A, Student Services Retrofit • LAC Parking Structure • LAC Building O Complex • LAC Infrastructure Improvements Project and District Wide – Energy Efficiency Project • LAC Building I (Bookstore) • PCC MDAB (Multi-Disciplinary Academic Building) • PCC Building CC Retrofit • District Wide – Electronic Signage Plan • LAC South Walkway Extension • LAC Math Technology Building • Q & A

  3. Current and UpcomingConstruction Projects LAC Building A – Student Services Retrofit Measure E 2008 • Received final DSA approval on 10/7/2010. • Project currently in bid process. Bids due 11/30. • Adds 6,500 Sq. Ft. to existing building • Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. • Estimated start of construction Winter 2010.

  4. Current and UpcomingConstruction Projects LAC Parking Structure – Measure E 2008 • Spaces for 900 Vehicles • Currently work is being done on the façade • Anticipated end of Construction Fall 2011

  5. Current and UpcomingConstruction Projects LAC Building O Complex – Measure E 2008 • Two structures totaling 87,000 square feet • Renovation of Building O1 began April 2010 • Anticipated completion Winter of 2010

  6. Current and UpcomingConstruction Projects LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 • Project to be completed in a phased construction schedule • Total annual estimated savings of 1.5 million Kwh • Project started Fall 2009; currently working on phase 6,7, and 8A • Landscaping upgrades to be implemented in conjunction with infrastructure project phasing • Majority of existing building HVAC systems to be upgraded and connected to the Central Plant • Exterior lighting and controls upgrades in progress • Anticipated end of construction Winter 2011

  7. Current and UpcomingConstruction Projects LAC Building I - Measure E 2008 • Adds additional 4,000 square feet to existing building • Architecture to match LAC Mediterranean Theme • BOT approved (10/26) for G2K Constr. • Notice To Proceed 11/15/10 • End of Construction anticipated Fall 2011

  8. Current and UpcomingConstruction Projects PCC MDAB (Multi-Disciplinary Academic Building) - Measure E 2002 • Notice To Proceed issued on 7/29/10 • Currently in phase 1 of construction (DD and EE in construction) • Portables for swing space installed Summer 2010 complete and occupied(MD Trailers) • Project to be completed in two phases

  9. Current and UpcomingConstruction Projects PCC Building CC Retrofit - Measure E 2008 • Currently in DSA for plan check (Structural) • Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices • Swing space located on PCC Campus (Bldg. GG) • To be completed concurrently with MDAB project phase 1 • Anticipated end of construction 2012

  10. Current and UpcomingConstruction Projects District Wide – Electronic Signage Plan Measure E 2008 • District Wide Signage Plan complete for LAC & PCC • LAC Daktronics digital sign going through final installation • PCC Daktronics digital sign currently being installed • Anticipated construction completion of Marquee Signs Fall 2010

  11. Current and UpcomingConstruction Projects LAC South Walkway Extension Measure E 2008 • 99% complete • Currently going through final punch-list • Continues Master Plan pedestrian corridor

  12. Current and UpcomingConstruction Projects Completed Schematic Design Will house Math and Culinary Arts instructional program as well as Reprographics Estimated start of construction Winter 2013 LAC Math Technology Building – Measure E 2008

  13. Liberal Arts Campus Site Plan l i b e r a l a r t s

  14. Pacific Coast Campus Site Plan p a c i f i c c o a s t

  15. Planned Phasing of Future Projects • 2010-11 • Begin construction of Building A at LAC – Fall 2010 • Begin Schematic Design for Buildings C and F at LAC • Submit plans to DSA no later than Summer 2011

  16. Planned Phasing of Future Projects • 2011-12 • Infrastructure project complete at LAC – Winter 2011 • Submit plans to DSA for Math/Technology Building at LAC – Summer 2012 • Construction completion of Buildings DD and EE at PCC – Fall 2011 • Begin construction of Buildings AA, BB and CC at PCC – Fall 2011 • Anticipated construction completion of Building I (Bookstore) at LAC – Fall 2011 • Anticipated construction completion of Parking Structure at LAC – Fall 2011

  17. Planned Phasing of Future Projects • 2012-13 • Move Buildings C and F programs into Swing Space (M/N Building) and begin construction – Summer 2012 • Anticipated Construction completion of Building A at LAC – Summer 2012 • Submit plans to DSA for M/N Building at LAC and Building MM (Phase 1) at PCC – Summer 2012 • Begin Schematic Design for Building P at LAC and Building MM (Phase 2) at PCC – Summer 2012 • Submit to DSA – Spring 2013 • Begin construction of Math/Technology Building at LAC – Winter 2013

  18. Planned Phasing of Future Projects • 2012-13 (continued) • Begin Schematic Design for Building D and E renovations – Fall 2013 • Anticipated Construction completion of Buildings AA, BB and CC at PCC – Summer 2013

  19. Planned Phasing of Future Projects • 2013-14 • Anticipated Construction completion of Buildings C and F at LAC – Fall 2013 • Begin construction of Buildings M/N at LAC and MM (Phase 1) at PCC – Fall 2013 • Submit plans to DSA for Buildings D and E renovations at LAC – Fall 2013 • Schematic design for Performing Arts Building (G & H) and Building R at LAC – Spring 2014

  20. Planned Phasing of Future Projects • 2014-15 • Anticipated Construction completion of Math/Technology Building at LAC – Summer 2014 • Begin construction on Buildings D and E at LAC – Fall 2014 • Submit plans to DSA for Performing Arts Building and Building R (Gym) at LAC – Spring 2015 • Anticipate construction start – Spring 2016 • Anticipated construction completion of Buildings M/N at LAC and MM at PCC – late Spring 2015 • Begin construction on Buildings P at LAC and MM (Phase 2) at PCC – Spring 2015

  21. QUESTIONS& ANSWERS EDUCATE ENGAGE EMPOWER