Riego localizado

Riego localizado. Práctico . 130m 0.5%. 150m. Cultivo: Manzana con pie enanizante Localidad: Canelones Marco de plantación: 2*4.5m Suelo de textura media a pesada Etc : Eto *kc * kloc. 180m 0.8%. Ejercicio 1. Etc : Eto *kc * kloc. Tabla de FAO: 1.2. Eto Las Brujas: 5.39 mm/d.

berg
Download Presentation

Riego localizado

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Riego localizado Práctico

  2. 130m 0.5% 150m • Cultivo: Manzana con pie enanizante • Localidad: Canelones • Marco de plantación: 2*4.5m • Suelo de textura media a pesada • Etc: Eto *kc *kloc 180m 0.8%

  3. Ejercicio 1 • Etc: Eto *kc *kloc Tabla de FAO: 1.2 Eto Las Brujas: 5.39 mm/d Gráfica de Fereres et al. 1981

  4. Etc= 5.39 *1.2 *0.75= 4.85 mm/d • Nt= 4.85/(0.85*0.90)= 6.34 mm/d • Necesidades totales • Eficiencia: 85 % • Coeficiente uniformidad: 90% • Dosis: 6.34 * 2 * 4.5= 57 litros

  5. Elección del gotero • Caudal nominal: 4.1 l/h • Espaciamientos: 0.3m, 0.4m, 0.5m, 0.6m, 0.75m, 1.00m y 1.25m • Chequear solapamiento: • Tipo de suelo y caudal Ecuación del gotero:

  6. Elegimos goteros a 0.75m • Tiempo de riego: • Dosis: 57 litros • Tasa de aplicación: Qgotero *Nº goteros= • = 4.1 l/h * 2.7=11.07 • Tiempo riego: 57/11.07= 5.15 horas • Número de sectores: 3 • Jornada: 15,45 horas

  7. OPCIÓN 1 130m 0.5% 150m 180m 0.8% Laterales de 130m Pendiente en contra: desnivel: 0.65m Tubería principal de 270m

  8. OPCIÓN 2 130m 0.5% 150m 180m 0.8% Laterales de 130m Pendiente a favor: desnivel: 0.65m Tubería principal de 400m

  9. OPCIÓN 3 130m 0.5% 150m 180m 0.8% Laterales de 65 m con pendiente en ambos sentidos Desnivel +- 0.325m Tubería principal de 335m

  10. OPCIÓN 3 • Laterales de 65m • Caudal: 65/0.75*4.1=355 l/h =0.099 l/s • CSM (87)= 0.352

  11. Tolerancia de caudales: Ps = MPa-(Pmin)s Ps = 4.310-(8.3)s=7.3m

  12. Tuberías disponibles: DN 17 y DN 20 Calculamos pérdidas de carga (Darcy-Weisbach) tubos.exe Caudal: 355 l/h.---- 0.099 l/s Long: 65m CSM: 0.352

  13. Calculo de presiones en el lateral (P inicial, P max, P min, P final) Lateral ascendente P inicial = Pa + ¾ hf + hg/2 = 10 + 0.75(0.862) + 0.325/2=10.8m P min = P max – hf -hg = 10.8 – (0.862) – 0.325 = 9.613m DPlateral= 10.8 – 9.613= 1.2m Pmin lateral descendente: 10.8 -t’hf = 10.8 – 0.70(0.862)= 10.2 m t‘ = 0.70 DPlateral= 10.8 – 10.2= 0.6m

  14. Diseño de la terciaria: 7.3 – 1.2 = 6.1 m (para el diseño de la terciaria) Probamos diferentes diámetros Caudal : 13 laterales * 0.099 * 2 = 2.57 l/s CSM= 0.366

  15. P MAX (t) = P inical (l) + ¾ hf (t) - hg(t)/2 P min(t) = P max(t) - t’hf(t) P MAX (t) = 10.8 + ¾ 3.4 – 0.45/2 = 13.125 m P min(t) = 13.125 – 0.88 (3.4)= 10.133m t‘ (0.45/3.4= 0.132) 0.88 PMINdel SECTOR= Pfinal (t) – hf(l)- hg(l) = 10.133- 0.862-0.325= 8.93m = Qmin=3.9 l/h CU final =93% con este nuevo valor de CU se recalculan las necesidades totales y se corrige el tiempo de riego • Nt= 4.85/(0.85*0.93)= 6.14 mm/d = 6.14*4.5*2=55 litros/planta • TR= 55/(4.1*2.7) = 5 horas DPsector= 13.125 – 8.93= 4.19 m

  16. Diseño de la tubería de conducción 130m 0.5% 150m A 180m 0.8% Longitud: 335m Hg(A) =1.4m Hg(B) =0.44m B

  17. Tuberías de conducción Longitud: 335m Caudal: 2.57 l/s Hg(A) =1.07m (215m con 0.5%) Hg(B) =0.11m (desde A hasta B(120m con 0.8%de pendiente a favor= 0.96m) hay desnivel a favor: 1.07 -0.96= 0.11 Cálculo de la potencia requerida para regar el sector mas alejado Carga requerida= Pmax.sector+ hfppal + hcabezal+hg= 13.12+17.04 +0.11+7=37.27m 13.12+5.45+0.11+7= 25.68

  18. 75