180 likes | 354 Views
Lake Washington Road project. Prepared for: Mr. Fran Lemieux Shaw Group. Client’s Project Goals. Shaw Group Development Corp. Design & cpnstruct xxx mi. m unicipal road Design & construct yy sf commercial office building MS Project construction schedule
E N D
Lake Washington Road project Prepared for: Mr. Fran Lemieux Shaw Group
Client’s Project Goals • Shaw Group Development Corp. • Design & cpnstruct xxx mi. municipal road • Design & construct yysf commercial office building • MS Project construction schedule • Project cost & cash flow analysis • Develop construction contract & terms
Project Management Plan • Project Consists of 3 parts • Project Controls • Project Scope • Project Schedule • Cash Flow Report • Transportation Design • Traffic analysis • Pavement design • Legal Aspects • Contract development & terms • Preparation for negotiations
Project Size and Cost • Road Design & Construction • Traffic analysis • Xx Mile municipal road • Estimated cost - $ ________ • Structure • 3 Storys • 62,523 sqfttotal • Estimated cost - $479,000 • Total Estimated Project Cost - $479,000
Transportation Design • Key Elements of the Design • Traffic Analysis • Pavement Design & Cost Estimating • Parking Lot Design
Traffic Analysis • Observed Traffic Counts • Space Coast TPO Transportation Data Management System • FDOT Trip Calculation Software • Pre/Post LOS Analysis for Babcock St. and University Blvd.
Pavement Design • AASHTO Guide For Design of Pavement Structures • Use of RAP (Recycled Asphalt Pavement) • 2007 RS Means • Precision Rock and Dredge – Palm Bay (Lime Stone) • VA Paving – Cocoa (HMA)
Parking Lot Design • City of Palm Bay Codes • ADA Guidelines • Lights by Outside Source Using ECO Lighting Solutions
Legal Aspects • Contract Development • Preparations for Negotiations
Contract Development-1 • Contract Development for Lake Washington Road • Description of lands/site • Contractors Responsibilities • Labor • Schedule • Permits • Owners Responsibilities • Communication • Payments • Insurance
Contract Development-2 • Bonds and Insurance/Surety • Change Orders • Claims • Tests and Inspections • Dispute Resolution • Good Faith Negotiations • Mediation • Arbitration • Litigation • Liquidated Damages
Negotiations • Preparation for Negotiations • Gather outside information on possible alternatives and prices to compare to. • Establish points of leverage that can be used during negotiation. • Set a goal or target maximum/minimum value that you are willing to buy/sell at. • Decide initial approach method (friendly negotiation/good cop-bad cop/etc…) • Through negotiations try to determine the oppositions stand point (do they NEED an agreement? do they have other options? Etc…) • Most importantly, always shoot for a Win/Win conclusion. If both parties can improve their situation and keep a friendly position with each other it will make it easier to negotiate again in the future.
Project summary • Schedule Timing • Cash Flow • Traffic Summary • Pavement Features • Contract Development • Negotiation Tactics
Thank you for choosing Shaw group • Project plan meets client’s goals • We will produce a quality project • We appreciate your business • I will be your project manager • My contact information is: • Michael Matern • 570-493-2053 • mmatern23@hotmail.com