CO2 cooling and IBL interface meeting Tooling cooling line at PP1. Didier Laporte CNRS – LPNHE Paris 06 février 2014 EDMS IN2P3 : I-036854 – V2. Assembling tooling. First cooling line. Montage splitter box, Début montage des lignes, soudure. 6/8 lines on tools. Fitting stoppers.
E N D
CO2 cooling and IBL interface meetingToolingcooling line at PP1 Didier Laporte CNRS – LPNHE Paris06 février 2014 EDMS IN2P3 : I-036854 – V2
First cooling line • Montage splitter box, • Début montage des lignes, soudure
In the pit, on scaffolding • LPSC table
Mainframe Elcom 20x20
Z table (axis) • Elcom
To do list : • Update of the lines (6 / 8 ), LAPP • Design side A, LPNHE • Splitter box interface, LAPP • Escargot interface, LAPP • Protection for travel, LPNHE • Connection links at PP1 (for tests), LPNHE • Command to do (Elcom), LAPP/LPNHE • Delivery date ?