RSRDC. UNIT-II JODHPUR. ORGANISATION CHART OF RSRDC UNIT-II JODHPUR. Financial Work Load in Unit. Rs. 4985.71 Lacs. Financial Work Load in Unit. Rs. In Lacs.
E N D
RSRDC UNIT-II JODHPUR
Financial Work Load in Unit Rs. 4985.71 Lacs
Financial Work Load in Unit Rs. In Lacs
Important Works Completed during last 5 years Civil and architectural work in superstructure of main power house building at GLTPP BARMERDATE OF START 18-2-05DATE OF COMP 17-5-06WORK IS COMPLETEDCOST OF WORK 449.61 LACS
Important Works Completed during last 5 yearsAREA DEVELOPMENT WORK SUCH AS WATERSUPPLY,SEVERAGE,ROAD AND DRAINAGE WORK IN VARIOUS RESIDENTIAL COLONIES &DEVELOPMENT OF LAND FILL SITES AT JODHPUR PACKAGE JOD-ST-O5DATE OF START 3-2-03DARE OF COMP 3-9-06COST 454.88 LACS
Residential Boys School Mandore Jodhpur Total Cost : Rs. 250.69 Lacs Location : Residential Boys School Mandore Jodhpur Date of Start : 27.06.08 Stipulated Date of Completion: 26.02.09 Expenditure till Date : Rs. 197.06 lacs Likely Completion date : Work Completed. Bottlenecks if any :
Important Works Completed during last 5 years ROB Rashala Road Jodhpur Completion Cost – Rs. 10.14 Crs.
Residential Boys School Kenpura Pali. Total Cost : Rs. 223.76 Crores Location : Construction of ROB in lieu of LC No. C-27 at Pali. Date of Start : 27.06.08 Stipulated Date of Completion: 26.02.09 Expenditure till Date : Rs.204.17 lacs Likely Completion date : Work is Completed.
Indoor Stadium Jodhpur Total Cost : Rs. 172.40 Crores Location : Jodhpur Date of Start : 04.07.07 Stipulated Date of Completion: 03.01.08 Expenditure till Date : Rs. 108.71 lacs Likely Completion date : On the availability of fund Bottlenecks if any : Funds are not made available by JDA
Strengthening & Dev. Pal Road MDM Circle to Boranada Jodhpur Total Cost : Rs. 51.60 Crores Location : Jodhpur Date of Start : 01.02.09 Stipulated Date of Completion: Expenditure till Date : Rs. 2900.00 lacs Likely Completion date : On the available of fund Bottlenecks if any : Funds are not made available by JDA
Constructionof LSQ&USQ at PTS Jodhpur Total Cost : Rs. 4.366 Crores Location : RPTC Campus Jodhpur Date of Start : 01.04.08 Stipulated Date of Completion : 28.02.09 Expenditure till Date : Rs. 332.03 lacs Likely Completion date : 31.12.09 Bottlenecks if any :
Construction of LSQ&USQ at RPTC Jodhpur Total Cost : Rs. 2.35 Crores Location : RPTC Campus Jodhpur Date of Start : 01.04.08 Stipulated Date of Completion : 28.02.09 Expenditure till Date : Rs. 244.56 lacs Likely Completion date : 31.12.09 Bottlenecks if any :
Construction of LSQ&USQ at RAC Ist Battalion Jodhpur Total Cost :Rs. 2.27 Crores Location : RPTC Campus & RAC Campus Jodhpur Date of Start : 25.02.08 Stipulated Date of Completion : 24.01.09 Expenditure till Date : Rs. 200.36 lacs Likely Completion date : 31.12.09 Bottlenecks if any :
Construction of “OIL HOUSE” at Jodhpur Total Cost : Rs. 8.50 Crores Location : Construction of “OIL HOUSE” at Jodhpur Date of Start : 22.07.08 Stipulated Date of Completion : 21.01.10 Expenditure till Date : Rs. 254.14 lacs Likely Completion date : 30.04.10 Bottlenecks if any : • Some decisions about RCC designs and finishing work are pending from OIL India Ltd. • Approval for subletting of some works like Aluminum and fire fighting is pending • Tenders for Electrical and AC works are not finalised.
Construction of ROB in lieu of LC No. C-27 at Pali. Total Cost : Rs. 12.00 Crores Location : Construction of ROB in lieu of LC No. C-27 at Pali. Date of Start : 19.10.08 Stipulated Date of Completion: 18.10.09 Expenditure till Date : Rs. 26.36 lacs Likely Completion date : Work is temporarily suspended. Bottlenecks if any : Revised A&F is required
Construction of ROB in lieu of LC No. 134-B at Abu Road. Total Cost : Rs. 10.00 Crores Location : Construction of ROB in lieu of LC No. 134-B at Abu Road. Date of Start : 12.09.08 Stipulated Date of Completion: 11.09.09 Expenditure till Date : Rs. 159.52 lacs Likely Completion date : 30.06.10 Bottlenecks if any : GAD was revised by RAILWAY delayed the work by 2 month . Some qty Steel supplied didn’t confirm to specifications and had to be replaced by supplier three times so work delayed by 3months..
BAR CHART FOR Construction of ROB in lieu of LC No. 134-B at Abu Road.