1 / 34

TSS Report on TEPPC, RS and WRS1.1 Marv Landauer August 24-26, 2011

TSS Report on TEPPC, RS and WRS1.1 Marv Landauer August 24-26, 2011. TEPPC Report. TEPPC Study Process. Activities 2029 Study Report approved in 2010 2019 and 2020 Study Reports approved t his year Ten Year Plan up for Board approval in September, then to DOE

dacia
Download Presentation

TSS Report on TEPPC, RS and WRS1.1 Marv Landauer August 24-26, 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TSS Report on TEPPC, RS and WRS1.1 Marv Landauer August 24-26, 2011

  2. TEPPC Report

  3. TEPPC Study Process Activities • 2029 Study Report approved in 2010 • 2019 and 2020 Study Reports approved this year • Ten Year Plan up for Board approval in September, then to DOE • Board version posted this week • Twenty year plan due in 2013 • Preparations being made to implement 2011 Study Plan

  4. Ten Year Plan Assumptions • Models depict expected 10 year future (2019 and 2020 studies) • RPS goals will be met • Foundational Transmission Projects will be built • Thermal generation efficiency information is from publically available information • Most required new generation was met by planned projects, some generic generation is added to fill the gap (highest capacity factor sites available)

  5. Ten Year Plan Assumptions • Forecast gas prices are used for all generation plus delivery charge (Henry Hub price was $7.28/MMBtuin 2010 dollars) • Load shape and hydro output based on actual 2006 operation • Wind and solar availability based on climatological data for 2006

  6. Ten Year Plan Assumptions • 121,000 GWh load added in WI • 900,000 GWh today in WI • Roughly 1% annual growth • 60% of growth is in CA, AB, CO and AZ • 54 GW generation added in 2020 • 210 GW existing generation capacity today • New generation: • 18 GW wind • 13 GW solar • 4 GW other renewables • 19 GW thermal • Results in 17% renewables WECC-wide in 2020

  7. Significant Generation Assumptions • 75% of CA RPS goals are met in state • 15,000 MW in CA is mostly solar and wind • CA Once-Through-Cooling (OTC) replacements • 8,000 MW of more efficient thermal generation added to replace 13,000 MW of old units • Other renewable additions – mostly wind • 6,000 MW in OR and WA • 600 MW in MT • 1200 MW in WY • 1400 MW in BC • Centralia and Hermiston still operating

  8. WECC RTEP Process Types of studies run • High/low gas price (+75%, -25%) • High/low hydro conditions • Carbon emissions, carbon adders • High/low load growth • High DSM/EE • Numerous transmission projects • Alternative regional resource development • High renewable development (MT and WY)

  9. Prod/Cost Study Issues ProMod Modeling Limitations • DC lines do not load as high as historical • Excess cycling of some generation • Dump Generation • Path loadings near limit • Limited Benchmarking with actual operation

  10. Prod/Cost Methodology

  11. WECC RTEP Process Ten Year Plan won’t include: • Selection of preferred projects to build • Cost allocation of projects • Quantification of impacts to specific ratepayers • Permitting/siting of projects

  12. WECC RTEP Process Study Conclusions in Ten Year Plan • Montana-NW Congestion • Pacific Intertie Congestion (COI and PDCI) • Consider expansion of transmission accessing renewable • Some remote resources appear to be cost effective • Need to study operational aspects of variable resources • Regional planning and cooperation • Consider environmental/cultural considerations next cycle • Consider water resource impacts in next cycle • Identify and fix caps in planning processes next cycle

  13. 2011 TEPPC Study Program • 2011 Study Program has been approved • For shorter term studies (ten years or less): • Developing 2010 benchmark base case • Developing 2022 common base case • Base cases planned to be ready in November • Case runs scheduled for the fall and winter

  14. High Priority 10-Year Study Cases

  15. Medium Priority 10-Year Study Cases 22

  16. Requests for Modeling Enhancements 23

  17. Timeline Extract from RTEP Project Timeline 2012

  18. TEPPC/TSS Coordination • TEPPC has uncovered system conditions with high wind penetration from Prod/Cost runs that merit study • Wind patterns, high transfers, reduced load, etc. • WECCs has promised DOE high level reliability analysis of these future plans • Initial steady state analysis attempted this year thru contactor by extracting power flow from prod/cost runs was mostly unsuccessful

  19. TEPPC/TSS Coordination • To find out if RPS goals are feasible, reliability studies of high wind penetration needed (steady state and transient studies, balancing requirements, etc.) • Does not appear these issues are getting sufficient attention • Is anyone looking at this? • If not, where/how should it be done? • TSS is logical home - expertise

  20. TEPPC/TSS Coordination • How can we combine load/generation conditions from ProMod and power flow/stability models for reliability analysis? • Can load/generation be extracted from ProMod and inserted into TSS case? • Can power flow extraction from ProMod be improved? • Can BCCS help in the long term? • Should joint TSS/TEPPC Task Force be created to delve into this issue?

  21. TEPPC/TSS Coordination • TEPPC has requested a ten-year case with high renewables and associated transmission in 2012 Study Program • Needed for future TEPPC study program • Integrating transmission needed with renewables • Could be used for reliability studies • Looks like it matches the 2023HS1 • How will this case be developed?

  22. Reliability Subcommittee Report

  23. August RS Meeting • Examination of Annual TRD outage data (5th year) • Development of SAR to align WECC Planning Criteria with new NERC TPL-001 Standard • Old NERC to new NERC • Old WECC Table W-1 (A, B, C, D) to P0 – P9 • Old NERC standard used “elements lost”, new NERC standard uses “initiating events” • Question: Will timing of composite load model/voltage dip requirements fit with this mapping? Should it remain a criterion?

  24. August RS Meeting • Reliability Metrics Work Group at NERC • New WECC Reliability Criteria Work Group under RPIC task: • Inventory WECC criteria • Determine whether to keep criteria or move to standard or guideline. • If there is insufficient criteria adherence => standard • Draft recommendation to RPIC in March 2012

  25. WRS1.1 Adjacent Circuit Criteria

  26. Adjacent Circuit Criteria: WRS1 and WRS1.1 • Drafting Team has developed consensus • Another draft is being circulated now with comments due September 6. • Goal is to bring proposed revised criteria to PCC in October • No-cascading idea did not have enough support to move it forward and was dropped. Staying with Level C performance

  27. Adjacent Circuit Criteria: WRS1 and WRS1.1 New Drafting Team Proposal: • Any two circuits within 250 feet are Adjacent Circuits • Intermediate circuits have no impact • Only applicable if BOTH circuits are above 300 KV • Criteria does not apply to internal systems • 3 mile total exemption for station entrances, river crossings, etc. • Clarified using both outage frequency and MTBF

More Related